Number
130233
Version
SUBSTITUTE 1
Reference
121550
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $1,014,700 for a total estimated cost of $1,101,000.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $1,014,700. The total estimated cost of these projects is $1,101,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:
4th Aldermanic District
N. Edison St. - E. State St. to E. Juneau Ave. (ST211110152) File Number 121550: Asphalt pavement resurfacing, replace all curb and gutter, replace all driveway approaches and replace sidewalk where necessary, sodding (5 - 8 foot width of tree border area), and grading. Also included, are permeable sidewalk and special drainage facilities. (Assessable Reconstruction Paving Fund -- $22,700; TID34 (TD03484050) Nonassessable Paving Fund -- $200,000). The total estimated cost for this project including the requested amount is $245,000. This project is anticipated to be completed during the 2013-2014 construction season.
5th Aldermanic District
Alley between W. Center St., W. Lorraine Pl., N. 82nd St., and N. 84th St. (ST212060104) File Number 040945: Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, and storm drainage...
Click here for full text