File #: 050408    Version: 0
Type: Resolution Status: Passed
File created: 7/6/2005 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 7/26/2005
Effective date:    
Title: Resolution authorizing and directing the Commissioner of Public Works to execute a revised project agreement titled "State/Municipal Agreement for a Highway Improvement Project" with the Wisconsin Department of Transportation to include updated construction costs for the rehabilitation of South Clement Avenue from South Whitnall Avenue to East Howard Avenue with Federal and State aid under the Surface Transportation Program. (Infrastructure Services Division)
Sponsors: THE CHAIR
Indexes: INTERGOVERNMENTAL AGREEMENTS, STREET IMPROVEMENTS, TRANSPORTATION, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Agreement.PDF, 2. Fiscal Note.PDF, 3. Infr. Serv. Div. Cover Letter.pdf, 4. Fiscal Analysis.pdf
Number
050408
Version
ORIGINAL
Reference
Sponsor
THE CHAIR
Title
Resolution authorizing and directing the Commissioner of Public Works to execute a revised project agreement titled "State/Municipal Agreement for a Highway Improvement Project" with the Wisconsin Department of Transportation to include updated construction costs for the rehabilitation of South Clement Avenue from South Whitnall Avenue to East Howard Avenue with Federal and State aid under the Surface Transportation Program. (Infrastructure Services Division)
Analysis
This resolution authorizes and directs the Commissioner of Public Works to execute a revised project agreement with the Wisconsin Department of Transportation WISDOT to include updated construction costs for the rehabilitation of the South Clement Avenue from South Whitnall Avenue to East Howard Avenue with Federal and State aid under the Surface Transportation Program. The total revised estimated construction cost for the project is $793,360, of which the City's share is $158,675. Construction funds will be included in a future Common Council resolution.
Body
Whereas, Common Council Resolution File Number 040400, adopted on July 27, 2004, authorized and directed the Commissioner of Public works to execute a project agreement with WISDOT for the programming and rehabilitation of South Clement Avenue from South Whitnall Avenue to East Howard Avenue with Federal and State aid under the Surface Transportation Program; and

Whereas, Preliminary engineering activities have begun and the project scope has changed from a reconstruction project to a resurfacing project; and

Whereas, Due to the change in scope the construction costs for the paving project have decreased from the original agreement; and

Whereas, The revised project agreement with the updated construction costs has been received from the WISDOT to be executed by the City of Milwaukee for the design and rehabilitation of the South Clement Avenue ...