Title: Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $35,000 for a total estimated cost of these projects being $305,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
11/14/20141 MAYOR SIGNED   Action details Meeting details Not available
11/5/20141 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Not available
10/22/20140 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Meeting convened at 9:04 am. Individual appearing: Mary Dziewiontkoski - Department of Public Works
Pass3:0 Roll call Meeting details Video Video
10/22/20141 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTIONPass4:0 Action details Meeting details Video Video
10/17/20140 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
10/17/20140 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
10/17/20140 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
10/14/20140 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
140973
Version
Substitute 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $35,000 for a total estimated cost of these projects being $305,000.
Analysis
This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed. After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable. A resolution will be submitted after the Public Hearing authorizing construction. The City cost for engineering these projects is estimated to be $35,000 with the total cost estimated to be $305,000.
Body
Resolved, By the Common Council of the City of Milwaukee that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:

7th Aldermanic District

Alley between W. Auer Ave., W. Hopkins St., N. 23rd St., and N. 24th St. (ST212160101): Paving the alley with concrete. Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $12,000). The total estimated cost for this project including the requested amount is $145,000. This project is anticipated to be completed during the 2016 construction season.

11th Aldermanic District

Alley between W. Forest Home Ave., W. Midland Dr., W. Wilbur Ave., S. 54th St., and S. 55th St. (ST212150115): Paving the alley with concrete. Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $13,000). The total estimated c...