powered help
header-left header-center header-right
File #: 231722    Version:
Type: Resolution Status: Passed
File created: 2/27/2024 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 3/19/2024
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $75,000 for a total estimated cost of these projects being $1,450,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Number
231722
Version
Substitute 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $75,000 for a total estimated cost of these projects being $1,450,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $75,000 with the total cost estimated to be $1,450,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

3rd Aldermanic District

N. Bremen St. - E. Garfield Ave. to E. North Ave. (SM495240014) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost of this project including the requested amount is $104,000. This project is anticipated to be completed during the 2024 construction season.

E. Garfield Ave. - N. Bremen St. to N. Weil St. (SM495240015) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost of this project including the requested amount is $180,000. This project is anticipated to be completed during the 2024 construction season.

6th Aldermanic District

N. Dr. William Finlayson St. - 550’ +/- South of W. Vienna Ave. to W. Vienna Ave. (SM495240013) Relaying storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost of this project including the requested amount is $171,000. This project is anticipated to be completed during the 2024 construction season.

6th Aldermanic District and the Village of Whitefish Bay

N. Santa Monica...