Number
071689
Version
ORIGINAL
Reference
Sponsor
THE CHAIR
Title
Resolution authorizes the Commissioner of Public Works and Comptroller to execute six Project Agreements with the Wisconsin Department of Transportation for traffic signal and roadway improvements and to fund preliminary engineering for these six projects in various Aldermanic Districts with a total estimated cost of $94,900.00, with an estimated grantor share of $80,910.00, and an estimated City share of $13,990.00.
Analysis
This resolution authorizes the Commissioner of Public Works and Comptroller to execute six Project Agreements with the Wisconsin Department of Transportation for the programming and construction of traffic signal and roadway improvements using Highway Safety Improvement Program funds for projects in various Aldermanic Districts. The total estimated cost of all six projects is $934,190.00, with a grantor share of $836,270.00, and a City share of $97,920.00. The total estimated preliminary engineering cost for these six projects is $94,900.00, with a grantor share of $80,910.00 and a City share of $13, 990.00, approval of construction costs will be in a future resolution.
Body
Whereas, The submittal of five Highway Safety Improvement Program (HSIP) grant applications to the Wisconsin Department of Transportation (WISDOT) was approved by the Common Council under File Number 061544; and
Whereas, The HSIP grant application for the installation of signal improvements at 13 intersections citywide was split into 2 projects to separate projects that are located on connecting highways; and
Whereas, Preliminary approval has been requested and received from WISDOT, along with six Project Agreements to be executed by the City of Milwaukee, for the programming and construction of six projects under the 2008 HSIP; and
Whereas, WISDOT has submitted six project agreements for execution by the City of Milwaukee for the design and construction of:
Project I.D. 2984-08-07/97
T...
Click here for full text