File #:
|
151418
Version:
|
|
|
Type:
|
Resolution
|
Status:
|
Passed
|
On agenda:
|
|
Final action:
|
2/9/2016
|
Title:
|
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $4,133,900 for a total estimated cost of $5,280,000.
|
Indexes:
|
PUBLIC IMPROVEMENTS, SPECIAL ASSESSMENTS
|
2/18/2016 | 1 |
MAYOR
| SIGNED | | |
Action details
|
Meeting details
|
Not available
|
2/9/2016 | 1 |
COMMON COUNCIL
| ADOPTED | Pass | 13:0 |
Action details
|
Meeting details
|
Video
|
1/27/2016 | 1 |
PUBLIC WORKS COMMITTEE
| RECOMMENDED FOR ADOPTION
Minutes note: Mary Dziewiontkoski - Deparment of Public Works
2nd Aldermanic District
W. Medford Ave. - W. Congress St. to N. 68th St. (TD04284001): Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (7-foot width of tree border area), and grading.
Ald. Bohl moved approval. (Prevailed 4-0)
3rd and 6th Aldermanic Districts
N. Pierce St. - E. Center St. to E. Burleigh St. (ST211120159): Concrete pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, narrow street from 38 feet to 36 feet, sodding (7-foot width of tree border area), and grading.
Ald. Kovac stated he had 10 in favor and 9 opposed, he stated the project is for a wider tree border, narrower street and traffic flow issues.
George Brush 3021 N Pierce St stated narrowing the street would be a disaster because of the bus traffic from Pierce School and this will not allow cars to pass in the winter.
Michael Ziedler 2737 N Pierce St stated he lives across the street from Pierce School and there are school buses and parent traffic that cause a lot of congestion. There is an automatic narrowing during the winter because of the snow.
Nancy Morris 2970 N Pierce St stated she and her renters don’t like the narrowing of the streets.
Ald. Bohl moved approval. (Prevailed 4-0)
5th Aldermanic District
N. 91st St. - W. Center St. to W. Locust St. (ST211150134): Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (9-foot width of tree border area), and grading.
Ald. Bohl moved approval. (Prevailed 4-0)
6th Aldermanic District
N. Holton St. - E. Capitol Dr. to E. Hope Ave. (ST211150173): Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (7-foot width of tree border area), and grading.
Ald. Wade moved approval. (Prevailed 3-0)
E. Hope Ave. - N. Richards St. to N. Holton St. (ST211150174): Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (7-foot width of tree border area), and grading.
Ald. Wade moved approval. (Prevailed 3-0)
7th Aldermanic District
N. 53rd St. - W. Roosevelt Dr. to W. Keefe Ave. (ST211150165): Concrete pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, sodding (6-foot width of tree border area), and grading.
Ald. Wade moved approval. (Prevailed 3-0)
8th Aldermanic District
S. 23rd St. - W. National Ave. to W. Pierce St. (ST211160109): Concrete pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, sodding (6-foot width of tree border area), and grading.
Ald. Donovan moved approval. (Prevailed 4-0)
S. 25th St. - W. National Ave. to W. Pierce St. (ST211060138): Asphalt pavement resurfacing, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, sodding (6-foot width of tree border area), and grading.
Ald. Donovan moved approval. (Prevailed 4-0)
9th Aldermanic District
W. Woolworth Ave. - N. Sherman Blvd. to N. 51st St. (ST211040107): Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (5-foot width of tree border area), and grading.
Ald. Bohl moved approval. (Prevailed 4-0)
11th Aldermanic District
W. Howard Ave. - W. Loomis Rd. to S. 43rd St. (Sponsored by the City of Greenfield) (ST211150181): Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (15-foot width of tree border area), and grading.
Ald. Wade moved approval. (Prevailed 4-0)
14th Aldermanic District
E. Stewart St. - S. Marina Dr. to S. Hilbert St. (ST21100147): Concrete pavement reconstruction, replace all curb and gutter, sidewalk and driveway approaches, sodding (5-foot width of tree border area), and grading.
Ald. Bohl moved approval. (Prevailed 4-0)
15th Aldermanic District
N. 32nd St. - W. Lisbon Ave. to W. North Ave. (ST211140129): Concrete pavement reconstruction, replace all curb and gutter, sidewalk and driveway approaches, sodding (7-foot width of tree border area), and grading.
Ald. Wade moved approval. (Prevailed 4-0) | Pass | 4:0 |
Action details
|
Meeting details
|
Video
|
1/19/2016 | 0 |
COMMON COUNCIL
| ASSIGNED TO | | |
Action details
|
Meeting details
|
Not available
|
|
Number 151418 Version SUBSTITUTE 1 Reference 150716 Sponsor THE CHAIR Title Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $4,133,900 for a total estimated cost of $5,280,000. Analysis This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $4,133,900. The total estimated cost of these projects is $5,280,000. Body Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements: 2nd Aldermanic District W. Medford Ave. - W. Congress St. to N. 68th St. (TD04284001/ST211160121): Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (7-foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $ 32,500); Nonassessable Reconstruction Paving Fund -- $5,000; TID-42 Funds $475,000). The total estimated cost for this project including the requested amount is $700,000. This project is anticipated to be completed during the 2016 construction season. 3rd and 6th Aldermanic Districts N. Pierce St. - E. Center St. to E. Burleigh St. (ST211120159) File Number 150716: Concrete pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, narrow street from 38 feet to 36 feet, sodding (7-foot width of tree border area), and grading. (Assessab... Click here for full text
|