Number
021757
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various assessable public improvements at various locations.
Analysis
This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed. After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable. A resolution will be submitted after the Public Hearing authorizing construction.
Body
Resolved, By the Common Council of the City of Milwaukee that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.60 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:
3rd Aldermanic District
N. Water St. – A point 200 feet m/l north of E. Pleasant St. to N. Holton St. Viaduct (ST211030142/TD04884006): Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where needed, sodding, and grading.
5th Aldermanic District
Alley between W. Fiebrantz Ave., W. Sarasota Pl., N. 99th St., and N. 100th St. (Sponsored by the City of Wauwatosa) (ST212040118): Paving the alley with asphalt. Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $3,500)
6th Aldermanic District
Alley between N. Bremen St., E. Meinecke Ave., E. Wright St., and N. Fratney St. (ST212040119): Paving the alley with concrete. Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $7,600)
8th Aldermanic District
W. Hayes Ave. (South Side) – S. 7th St. to S. 8th St. (SM211030131): Removing and replacing all curb and gutter. Removing and re...
Click here for full text