powered help
header-left header-center header-right
File #: 190396    Version:
Type: Resolution Status: Passed
File created: 6/18/2019 In control: COMMON COUNCIL
On agenda: Final action: 7/9/2019
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $758,600 for a total estimated cost of $788,600.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Signed Letter.pdf, 2. Signed Ad.pdf, 3. Offical Ad 14.pdf, 4. Proof of Publication
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
7/19/20191 MAYOR SIGNED   Action details Meeting details Not available
7/9/20191 COMMON COUNCIL ADOPTEDPass14:0 Action details Meeting details Video Video
6/26/20190 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Mary Dziewiontkoski - DPW 2nd Aldermanic District N. 62nd St. – W. Hope Ave. to W. Marion St. (ST211190118) Install traffic calming speed hump(s). Ald. Johnson moved approval. (Prevailed 5-0) N. 74th St. – W. Marion St. to W. Congress (ST211180266) Install traffic calming speed hump(s). Ald. Johnson moved approval. (Prevailed 5-0) 7th Aldermanic District N. 45th St. – W. Concordia Ave. to W. Townsend St. (ST211180276) Install traffic calming speed hump(s). Ald. Kovac moved approval. (Prevailed 5-0) 9th Aldermanic District W. Denver Ave. – N. Burbank Ave to N. 91st St. (ST211180110) Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (21’ width of tree border area), and grading. Ald. Murphy moved approval. (Prevailed 5-0)
Pass5:0 Action details Meeting details Video Video
6/18/20190 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
190396
Version
SUBSTITUTE 1
Reference
160695
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $758,600 for a total estimated cost of $788,600.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $758,600. The total estimated cost of these projects is $788,600.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

2nd Aldermanic District

N. 62nd St. - W. Hope Ave. to W. Marion St. (ST211190118) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $8,000; Nonassessable Reconstruction Paving Fund -- $2,000) The total estimated cost for this project including the requested amount is $10,000. This project is anticipated to be completed during the 2019 construction season.

N. 74th St. - W. Marion St. to W. Congress (ST211180266) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $6,300; Nonassessable Reconstruction Paving Fund -- $2,000) The total estimated cost for this project including the requested amount is $8,300. This project is anticipated to be completed during the 2019 construction season.

7th Aldermanic District

N. 45th St. - W. Concordia Ave. to W. Townsend St. (ST211180276) Install traffic calming speed hump(s). (Assessable Reconstruction Pa...

Click here for full text