File #: 090909    Version:
Type: Resolution Status: Passed
File created: 11/3/2009 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 12/1/2009
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $104,000 for a total estimated cost of these projects being $1,465,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Cover Letter, 2. Hearing Notice List, 3. Fiscal note
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
12/9/20091 MAYOR SIGNED   Action details Meeting details Not available
12/1/20091 COMMON COUNCIL ADOPTEDPass14:0 Action details Meeting details Not available
11/18/20091 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Individual present: Clark Wantoch, Dept. of Public Works, Infrastructure Services
Pass5:0 Action details Meeting details Not available
11/10/20090 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
11/3/20090 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
090909
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $104,000 for a total estimated cost of these projects being $1,465,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $104,000 with the total cost estimated to be $1,465,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

1st Aldermanic District

W. Atkinson Ave. (north side) - N. 20th St. to N. 21st St. (SM495090099): Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost for this project including the requested amount is $108,000. This project is anticipated to be completed during the 2010 construction season.

4th Aldermanic District

N. Plankinton Ave. - W. Wisconsin Ave. to W. Wells St. (WT410091028): Relaying water main. (Nonassessable Water Fund -- $15,000). The total estimated cost for this project including the requested amount is $400,000. This project is anticipated to be completed during the 2010 construction season.

6th Aldermanic District

E. North Ave. - N. Buffum St. to N. Hubbard St. (SM495090098): Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost for this project including the requested amount is $110,000. This project is anticipated to be completed during the 2010 construction season.

8th Aldermanic District

W. Montana St. - S. 29th St. to S. 33rd St. (SM4...