Number
241870
Version
ORIGINAL
Reference
Sponsor
THE CHAIR
Title
Resolution authorizing the Commissioner of Public Works and Comptroller to execute utility agreements with the Wisconsin Department of Transportation for work on city facilities in conjunction with the I-94 East West, West Leg (70th Street - Zablocki Drive) contract work with a total estimated cost of $486,960, with an estimated grantor share of $438,264 and an estimated City share of $48,696.
Analysis
This resolution authorizes the Commissioner of Public Works and Comptroller to execute various Agreements for Payment for Relocation or Replacement of Municipal Utility Facilities Located on Public Held Land Required by Freeway Construction for various city facilities.
These agreements relate to utility work on city facilities necessitated by the construction of the I-94 East West, West Leg (70th Street - Zablocki Drive), being undertaken by the Wisconsin Department of Transportation. This agreement provides for reimbursement from the Wisconsin Department of Transportation of 90 percent of City costs for all work on city facilities necessitated by the freeway reconstruction project in accord with Wisconsin State Statute 84.295(4m).
This resolution also authorizes the Commissioner of Public Works to prepare and/or review plans and estimates for the I-94 East West, West Leg utility work as necessary to accomplish the project. This resolution also authorizes the Comptroller to establish accounts as necessary to track the work and to submit invoices to the Wisconsin Department of Transportation for work completed on this project as approved by the Commissioner of Public Works, for a total amount of $486,960, with an estimated grantor share of $438,264 and an estimated City share of $48,696.
Body
Whereas, The State of Wisconsin Department of Transportation has scheduled the reconstruction of I-94 East West, West Leg (70th Street - Zablocki Drive) in the City of Milwaukee, Milwaukee County; a...
Click here for full text