File #:
|
161439
Version:
|
|
|
Type:
|
Resolution
|
Status:
|
Passed
|
On agenda:
|
|
Final action:
|
3/1/2017
|
Title:
|
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $1,185,000 for a total estimated cost of $1,623,000.
|
Indexes:
|
PUBLIC IMPROVEMENTS
|
3/10/2017 | 1 |
MAYOR
| SIGNED | | |
Action details
|
Meeting details
|
Not available
|
3/1/2017 | 1 |
COMMON COUNCIL
| ADOPTED | Pass | 15:0 |
Action details
|
Meeting details
|
Video
|
2/15/2017 | 0 |
PUBLIC WORKS COMMITTEE
| RECOMMENDED FOR ADOPTION
Minutes note: Mary Dziewiontkoski - DPW
1st Aldermanic District
N. 16th St. - W. Capitol Dr. to W. Fiebrantz Ave. (ST211170134):
Install traffic calming speed hump(s).
Bruce Wright 4075 N 16th St stated he is in support of the speed hump.
Arlisia McHenry 1st District Chief of Staff stated she would like all the projects held one cycle for neighborhood discussions.
Deshea Agee 4035 N 16th St stated he is in support of the speed hump.
Ald. Donovan moved to Hold to the Call of the Chair. (Prevailed 5-0)
N. 38th St. - W. Villard Ave. to W. Rohr Ave. (ST211170113):
Install traffic calming speed hump(s).
Ald. Donovan moved to Hold to the Call of the Chair. (Prevailed 5-0)
N. 42nd St. - W. Thurston Ave. to W. Florist Ave. (ST211170115):
Install traffic calming speed hump(s).
Ald. Donovan moved to Hold to the Call of the Chair. (Prevailed 5-0)
2nd Aldermanic District
N. 69th St. - W. Capitol Dr. to W. Hope Ave. (ST211150125):
Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (9-foot width of tree border area), and grading.
Todd Miller 2nd District Legislative Assistant stated Ald. Johnson is in support.
Ald. Bauman moved approval. (Prevailed 5-0)
N. 75th St. - W. Beckett Ave. to W. Congress St. (ST211150126):
Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (9-foot width of tree border area), and grading.
Ald. Bauman moved approval. (Prevailed 5-0)
3rd Aldermanic District
Alley between N. Farwell Ave., E. Linnwood Ave., E. Locust St., and N. Prospect Ave. (ST212060108):
Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, storm drainage facilities, and permeable pavement as necessary.
Gary Steinhafel 2952 N Farwell Ave stated the alley is horrible and needs to be replaced.
Ald. Kovac stated most neighbors are opposed to the project, 8 neighbors were against it and 6 neighbors were for it.
Ald. Kovac moved denial of the project. (Prevailed 5-0)
7th Aldermanic District
N. 28th St. - W. Locust St. to W. Chambers St. (ST211170136):
Install traffic calming speed hump(s).
Ald. Donovan moved approval. (Prevailed 5-0)
N. 44th St. - W. Hadley St. to W. Locust St. (ST211170137):
Install traffic calming speed hump(s).
Ald. Bauman moved approval. (Prevailed 5-0)
N. 54th Blvd. - W. Keefe Ave. to W. Melvina St. (ST211170119):
Install traffic calming speed hump(s).
Ald. Bohl moved approval. (Prevailed 5-0)
Alley between W. Keefe Ave., W. Medford Ave., W. Roosevelt Dr., W. Scranton Pl., and N. 45th St. (ST212080102):
Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, storm drainage facilities, and permeable pavement as necessary.
Ald. Kovac moved approval. (Prevailed 5-0)
8th Aldermanic District
W. Scott St. - S. 30th St. to S. 31st St. (ST211170128):
Install traffic calming speed hump(s).
Ald. Donovan moved approval. (Prevailed 5-0)
S. 29th St. - W. Forest Home Ave. to W. Hayes Ave. (ST211170132):
Install traffic calming speed hump(s).
Ald. Donovan stated he received 7 postcards in opposition.
Ald. Donovan moved denial. (Prevailed 5-0)
S. 36th St. - W. National Ave. to W. Pierce St. (ST211170131):
Install traffic calming speed hump(s).
Ald. Donovan moved approval. (Prevailed 5-0)
Alley between W. Greenfield Ave., S. Layton Blvd., W. Scott St., and S. 28th St. (ST212140104):
Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, storm drainage facilities, and permeable pavement as necessary.
David Lehmen 1311 S Layton Blvd stated he has no access to the alley.
Ald. Donovan moved approval. (Prevailed 5-0)
10th Aldermanic District
W. Nash St. - N. 62nd St. to a point 150 feet m/l west of N. 64th St. (ST211080104):
Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (7-foot width of tree border area), and grading.
Edwin Huertas 10th District Legislative Assistant stated Ald. Murphy is in support.
Ald. Kovac moved approval. (Prevailed 5-0)
N. 63rd St. - W. Nash St. to a point 450 feet m/l north of W. Nash St. (ST211070101):
Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (7-foot width of tree border area), and grading.
Edwin Huertas 10th District Legislative Assistant stated Ald. Murphy is in support.
Ald. Bohl moved approval. (Prevailed 5-0)
N. 64th St. - W. Nash St. to a point north of W. Nash St. (ST211070102):
Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (7-foot width of tree border area), and grading.
Edwin Huertas 10th District Legislative Assistant stated Ald. Murphy is in support.
Ald. Bauman moved approval. (Prevailed 5-0)
Alley between W. Auer Ave., W. Burleigh St., N. 54th St., and N. 55th St. (north-south leg) (ST212160113):
Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, storm drainage facilities, and permeable pavement as necessary.
Edwin Huertas 10th District Legislative Assistant stated Ald. Murphy is in support.
Ald. Donovan moved approval. (Prevailed 5-0)
Alley between W. Main St., S. 61st St., S. 62nd St., and lands north (ST212160110):
Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, storm drainage facilities, and permeable pavement as necessary.
Edwin Huertas 10th District Legislative Assistant stated Ald. Murphy is in support.
Ald. Kovac moved approval. (Prevailed 5-0)
11th Aldermanic District
S. 82nd St. - W. Morgan Ave. to W. Holt Ave. (ST211150110):
Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (8-foot width of tree border area), and grading.
Ald. Borkowski stated residents were in support.
Ald. Bohl moved approval. (Prevailed 4-0)
S. 85th St. - W. Morgan Ave. to W. Holt Ave. (ST211150162):
Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (8-foot width of tree border area), and grading.
Ald. Borkowski stated the majority of residents were in support.
Ald. Bauman moved approval. (Prevailed 4-0)
Alley between W. Cleveland Ave., W. Montana St., S. 49th St., and S. 50th St. (ST212060106):
Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, storm drainage facilities, and permeable pavement as necessary.
Ald. Borkowski stated he has some concerns and asked that the project be held.
Ald. Bohl moved to Hold to the Call of the Chair. (Prevailed 4-0)
13th Aldermanic District
S. 21st St. - W. Van Norman Ave. to W. Whitaker Ave. (ST211150160):
Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (8-foot width of tree border area), and grading.
Herman Rodriguez 4360 S 21st St stated he wants to make sure he will have access because his son is handicapped.
Ald. Bauman moved to Hold to the Call of the Chair. (Prevailed 4-0)
14th Aldermanic District
E. Smith St. - S. Howell Ave. to S. Burrell St. (ST211170127):
Install traffic calming speed hump(s).
Ald. Zielinski stated residents are in support.
Ald. Bohl moved approval. (Prevailed 4-0)
S. 11th St. - W. Oklahoma Ave. to W. Montana St. (ST211170144):
Install traffic calming speed hump(s).
Ald. Zielinski stated residents are in support.
Ald. Bohl moved approval. (Prevailed 4-0)
Ald. Bauman moved approval as amended. (Prevailed 4-0)
| Pass | 4:0 |
Action details
|
Meeting details
|
Video
|
2/7/2017 | 0 |
COMMON COUNCIL
| ASSIGNED TO | | |
Action details
|
Meeting details
|
Not available
|
|
Number 161439 Version SUBSTITUTE 1 Reference 131585 Sponsor THE CHAIR Title Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $1,185,000 for a total estimated cost of $1,623,000. Analysis This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $1,185,000. The total estimated cost of these projects is $1,623,000. Body Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements: 2nd Aldermanic District N. 69th St. - W. Capitol Dr. to W. Hope Ave. (ST211150125) File Number 131585: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (9-foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $16,500; Nonassessable Reconstruction Paving Fund -- $90,000). The total estimated cost for this project including the requested amount is $125,000. This project is anticipated to be completed during the 2017 construction season. N. 75th St. - W. Beckett Ave. to W. Congress St. (ST211150126): File Number 131585: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (9-foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $21,500; Nonassessable Reconstruction Paving Fund -- $155,000). The tota... Click here for full text
|