Number
221440
Version
SUBSTITUTE 1
Reference
200576
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $3,265,713.84 for a total estimated cost of $9,708,236.84.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $3,265,713.84. The total estimated cost of these projects is $9,708,236.84.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:
1st and 7th Aldermanic Districts
W. Hampton Ave. - N. 29th St. to N. 60th St. (ST3201904XX) (2545-09-71) File Number 200576: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (7‘ width of tree border area), signals, street lighting and grading. This project is anticipated to be completed during the 2023 construction season.
Grantor Non-Reimbursable Paving Fund - $5,602,193.91
Grantor Reimbursable Paving Fund -- $840,329.09
City Share Assessable Paving Fund -- $46,300
City Share Non-Assessable Paving Fund - $3,219,413.84
These funds are to be transferred to the construction account (ST3201904XX) (2545-09-71)
Previously authorized for project construction: $0.00
Current estimated cost of total project including this resolution: $10,746,024.84
Original estimated cost of total project (File Number 181577): $1,037,788
...
Click here for full text