powered help
header-left header-center header-right
File #: 131376    Version:
Type: Resolution Status: Passed
File created: 1/22/2014 In control: COMMON COUNCIL
On agenda: Final action: 2/11/2014
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,104,000 for a total estimated cost of these projects being $2,053,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Hearing Notice List
Number
131376
Version
Substitute 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,104,000 for a total estimated cost of these projects being $2,053,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $1,104,000 with the total cost estimated to be $2,053,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

1st Aldermanic District

N. 23rd St. - 310 feet m/l south of W. Hope Ave. to W. Hope Ave. (SM495140005): Relaying storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost for this project including the requested amount is $71,000. This project is anticipated to be completed during the 2014 construction season.

3rd Aldermanic District

N. Farwell Av. - E. Brady St. to E. Royall Pl. (SM495120310): Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $70,000, Additional Funds). The total estimated cost for this project including the requested amount is $176,000. This project is anticipated to be completed during the 2014 construction season.

6th Aldermanic District

E. Clarke St. - N. Hubbard St. to N. Richards St. (SM495140006): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost for this project including the requested amount is $83,000. This project is anticipated to be completed during the 2014 construction season.

W. Wright St. - N. Palmer Av...

Click here for full text