Number
240646
Version
ORIGINAL
Reference
Sponsor
THE CHAIR
Title
Resolution authorizing the City Comptroller to transfer funds to the previously established project for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the construction of the 20th Street Power Line and Beerline Trail Project with a total estimated cost increase for the project of $0.
Analysis
Resolution authorizing the City Comptroller to transfer funds to the previously established projects for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the construction of the 20th Street Power Line and Beerline Trail Project with a total estimated cost increase for the project of $0.
Body
Whereas, The City of Milwaukee is performing the Let for the construction project; and
Whereas, Additional grantor reimbursable funds are, therefore, necessary to complete the construction of the project; now, therefore be it
Resolved, By the Common Council of the City of Milwaukee, that the City Comptroller is hereby authorized to transfer fund to the project grant chart field as follows:
Project Grant Value
State ID 2984-22-75
ST320210210
20th Street Power Line and Beerline Trail
Olive Street to Villard Avenue & 24th Street to 20th Street
City Share Non-Assessable Paving Fund
ST320240000
Fund 0333
$0
Grantor Reimbursable
SP032240100
Fund 0306
$674,374
Grantor Non-Reimbursable
$(674,374)
Estimated Total Construction - $0
Total construction previously authorized $1,292,968
Current estimated cost of total project including this resolution $1,437,407.55
Original estimated cost of total project (Resolution File Number 201243) $981,139
Requestor
Department of Public Works
Drafter
Infrastructure Services Division
CHAD CHRISBAUM:K. Vos
August 26, 2024