powered help
header-left header-center header-right
File #: 240648    Version: 0
Type: Resolution Status: Passed
File created: 9/3/2024 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 9/24/2024
Effective date:    
Title: Resolution authorizing the City Comptroller to transfer additional funds to the previously established project for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the construction of North 76th Street Intersection with Hampton Avenue with a total estimated cost increase for the project of $275,680.92, with an estimated Grantor share of $0, and an estimated City share of $275,680.92.
Sponsors: THE CHAIR
Indexes: INTERGOVERNMENTAL AGREEMENTS, STREET IMPROVEMENTS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Shortfall Resolution 76th and Hampton.pdf, 2. Resolution Certification 2545-03-72.pdf

Number

240648

Version

ORIGINAL

Reference

Sponsor

THE CHAIR

Title

Resolution authorizing the City Comptroller to transfer additional funds to the previously established project for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the construction of North 76th Street Intersection with Hampton Avenue with a total estimated cost increase for the project of $275,680.92, with an estimated Grantor share of $0, and an estimated City share of $275,680.92.

Analysis

Resolution authorizing the City Comptroller to transfer additional funds to the previously established projects for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the construction of North 76th Street Intersection with Hampton Avenue with a total estimated cost increase for the project of $275,680.92, with an estimated Grantor share of $0, and an estimated City share of $275,680.92.

Body

Whereas, Additional funds are, therefore, necessary to complete the construction of the projects; now, therefore be it

 

Resolved, By the Common Council of the City of Milwaukee, that the City Comptroller is hereby authorized to transfer fund to the project grant chart field as follows:

 

Project Grant Value

State ID 2545-03-72

ST320190610

North 76th Street

Intersection with Hampton Avenue

 

City Share Non-Assessable Paving Fund

ST320240000

Fund 0333

$275,680.92

 

Grantor Reimbursable

SP032240100

Fund 0306

$0

 

Grantor Non-Reimbursable

$0

 

Estimated Additional Construction - $275,680.92

 

Total construction previously authorized $1,070,219.69

Current estimated cost of total project including this resolution $1,569,900.61

Original estimated cost of total project (Resolution File Number 181690) $885,130

Requestor

Department of Public Works

Drafter

Infrastructure Services Division

DAVID J TAPIA:K. Vos

August 26, 2024