File #: 180397    Version:
Type: Resolution Status: Passed
File created: 6/20/2018 In control: COMMON COUNCIL
On agenda: Final action: 7/10/2018
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $1,219,600 for a total estimated cost of $1,297,600.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SPECIAL ASSESSMENTS
Attachments: 1. Signed Letter Cycle 14.pdf, 2. Official Notice, 3. Notice Published on 7-26-18
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
7/26/20181 CITY CLERK PUBLISHED   Action details Meeting details Not available
7/19/20181 MAYOR SIGNED   Action details Meeting details Not available
7/10/20181 COMMON COUNCIL ADOPTEDPass14:0 Action details Meeting details Video Video
6/27/20180 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Mary Dziewiontkoski - DPW 2nd Aldermanic District N. 73rd St. -- W. Capitol Dr. to W. Congress St. (ST211180107) Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (8’ width of tree border area), and grading. Ald. Johnson stated he is in support. Ald. Borkowski moved approval. (Prevailed 3-0) 5th Aldermanic District N. 85th St. - W. Locust St. to W. Burleigh St. (ST211150169) Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (8’ width of tree border area), and grading. Mark Cavendish 2919 N 85th St is in support of the project. Ald. Borkowski moved approval. (Prevailed 4-0) 7th and 15th Aldermanic District W. Locust St. - N. 29th St. to W. Fond du Lac Ave. (ST211180118) Concrete pavement reconstruction, replace all curb and gutter, sidewalk and driveway approaches, sodding (3’ width of tree border area), and grading. Ald. Kovac moved approval. (Prevailed 4-0) 8th Aldermanic District S. 34th St. - W. Lincoln Ave. to W. Grant St. (ST211180201) Install traffic calming speed hump(s). Ruth Kopp 2248 S 34th St stated she does not see enough traffic or excessive speeding to warrant a speed hump. Ald. Donovan moved to delete the project. (Prevailed 4-0) S. 37th St.-W. Margaret Pl. to W. Hilda Pl. (ST211180202) Install traffic calming speed hump(s). Norman Currie 1266 S 37th St stated he is opposed to the speed hump because he doesn’t see any speeders. Ald. Donovan moved to delete the project. (Prevailed 4-0) 10th Aldermanic District W. Auer Ave. - N. 56th St. to N. 58th St. (ST211180217) Install traffic calming speed hump(s). Ald. Borkowski moved approval. (Prevailed 4-0) 12th Aldermanic District W. Walker St. - S. 14th St. to S. 15th St. (ST211180209) Install traffic calming speed hump(s). Ald. Kovac moved approval. (Prevailed 4-0) 15th Aldermanic District N. 24th St. -- W. Vliet St. to W. Cherry St. (ST211180199) Install traffic calming speed hump(s). Ald. Donovan moved approval. (Prevailed 4-0) N. 26th St. -- W. Lisbon Ave. to W. Vine St. (ST211180211) Install traffic calming speed hump(s). Ald. Kovac moved approval. (Prevailed 4-0) N. 50th St. -- W. Clarke St. to W. Center St. (ST211180204) Install traffic calming speed hump(s). Ald. Borkowski moved approval. (Prevailed 4-0) Ald. Kovac moved approval as amended. (Prevailed 4-0)
Pass4:0 Action details Meeting details Video Video
6/20/20180 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number
180397
Version
SUBSTITUTE 1
Reference
160587
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $1,219,600 for a total estimated cost of $1,297,600.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $1,219,600. The total estimated cost of these projects is $1,297,600.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

2nd Aldermanic District

N. 73rd St. -- W. Capitol Dr. to W. Congress St. (ST211180107) File Number 160587: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding ( 8’ width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $48,000; Nonassessable Reconstruction Paving Fund -- $450,000). The total estimated cost for this project including the requested amount is $525,000. This project is anticipated to be completed during the 2018-19 construction season.

5th Aldermanic District

N. 85th St. - W. Locust St. to W. Burleigh St. (ST211150169) File Number 140430: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding ( 8’ width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $23,000; Nonassessable Reconstruction Paving Fund...

Click here for full text