File #: 241883    Version:
Type: Resolution Status: In Council-Adoption
File created: 4/2/2025 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action:
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $12,363,409.53 for a total estimated cost of these projects being $23,743,709.53.
Sponsors: THE CHAIR
Attachments: 1. Resolution Certification 2615-15-73.pdf
Number
241883
Version
Substitute 1
Reference
220499
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $12,363,409.53 for a total estimated cost of these projects being $23,743,709.53.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $12,363,409.53. The total estimated cost of these projects is $23,743,709.53.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

4th and 12th Aldermanic Districts

16th Street Bridge - Bridge over the Menomonee River (BR3202217XX/ST3202217XX) (2615-15-73). File Number 220499: Bridge rehabilitation. This project is anticipated to be constructed in the 2025 construction season.

Grantor Non-Reimbursable Paving Fund $157,218.26
Grantor Reimbursable Paving Fund $23,582.74
City Share Non-Assessable Paving Fund $821,219.30
Grantor Non-Reimbursable Structure Fund -- $9,041,181.74
Grantor Reimbursable Structure Fund -- $1,356,177.26
City Share Non-Assessable Structure Fund -- $8,037,430.23

These funds are to be transferred to the construction account (BR3202217XX/ST3202217XX) (2615-15-73)

Previously authorized for project construction: $0.00
Current estimated cost of construction including this resolution: $19,436,809.53
Original estimated cost of the project (File Number 220499): $14,983,600.00
Current estimated total cost of the project including this resolution: $21,192,709.53
7th Aldermanic District

N. 28th ...