Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $68,000 for a total estimated cost of these projects being $674,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, WATER MAINS
Attachments: 1. Hearing Notice List
Number
110690
Version
Substitute 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $68,000 for a total estimated cost of these projects being $674,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $68,000 with the total cost estimated to be $674,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

5th Aldermanic District

W. Townsend St. - N. 76th St. to N. 82nd St. (SM495110540): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $17,300, Additional Funds). The total estimated cost for this project including the requested amount is $37,300. This project is anticipated to be completed during the 2011 construction season.

10th Aldermanic District

S. 60th St. - W. Dickinson St. to W. Main St. (SM495110528): Sewer work prior to paving. (Nonassessable Sewer Maintenance Relay Fund -- $3,000, Additional Funds). The total estimated cost for this project including the requested amount is $20,000. This project is anticipated to be completed during the 2011 construction season.

11th Aldermanic District

W. Wedgewood Dr. - S. Sunset Dr. to S. Massachusetts Ave. (WT410120001): Relay water main. (Nonassessable Water Fund Budget Line 5010 -- $10,000; Nonassessable Water Fund Budget Line 6410 -- $10,000). The total estimated cost for this project including the requested amount is $280,000. This project is anticipated to be completed during the 20...