Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $2,450,000 for a total estimated cost of these projects being $2,761,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $2,450,000. The total estimated cost of these projects is $2,761,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
1st Aldermanic District
W. Lawn Ave. - 500 feet west of N. 13th St. to 800 feet west of N. 13th St. (WT410100024) File Number 091432: Relaying water main. (Nonassessable Water Fund Budget Line 6410 -- $75,000). The total estimated cost for this project including the requested amount is $90,000. This project is anticipated to be completed during the 2010 construction season.
6th Aldermanic District
W. North Ave. - N. Dr. Martin Luther King Jr. Dr. to N. 7th St. (TD05988006) File Number 070284: Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (TID Nonassessable Paving Fund -- $500,000). The total estimated cost for this project is $500,000. This project is anticipated to be completed during the 2010 construction season.
9th Aldermanic District
County Line Bridge over the Little Menomonee River (BR320080101) File Number 080846: Bridge replacement and concrete pavement bridge approac...