File #: 100735    Version: 0
Type: Resolution Status: Passed
File created: 10/12/2010 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 11/3/2010
Effective date:    
Title: Resolution relative to the cost participation and installation of traffic control signal and sign improvements on South 27th Street from a point north of West Kinnickinnic River Parkway to a point north of West Howard Avenue under a Highway Safety Improvement Program project in the 8th, 11th, and 13th Aldermanic Districts at a total estimated cost of $113,413.30, with an estimated grantor share of $102,071.97, and an estimated City share of $11,341.33.
Sponsors: THE CHAIR
Indexes: AGREEMENTS, TRAFFIC CONTROL SIGNALS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Cover Letter, 2. Agreement, 3. Comptroller's Certificate, 4. Fiscal Impact Statement, 5. Hearing Notice List, 6. Executed Contract
Number
100735
Version
ORIGINAL
Reference

Sponsor
THE CHAIR
Title
Resolution relative to the cost participation and installation of traffic control signal and sign improvements on South 27th Street from a point north of West Kinnickinnic River Parkway to a point north of West Howard Avenue under a Highway Safety Improvement Program project in the 8th, 11th, and 13th Aldermanic Districts at a total estimated cost of $113,413.30, with an estimated grantor share of $102,071.97, and an estimated City share of $11,341.33.
Analysis
This resolution authorizes the Commissioner of Public Works and Comptroller to enter into a funding agreement for the installation of traffic control signal and sign improvements on South 27th Street from a point north of West Kinnickinnic River Parkway to a point north of West Howard Avenue under a Highway Safety Improvement Program project in the 8th, 11th, and 13th Aldermanic Districts at a total estimated cost of $113,413.30, with an estimated grantor share of $102,071.97, and an estimated City share of $11,341.33, and to install these improvements upon execution of the agreement. This resolution also authorizes the Comptroller to establish and transfer funds to the appropriate accounts for the project. The total estimated cost of the entire project is $414,114.00, with a grantor share of $372,702.00 and a City share of $41,412.00.
Body
Whereas, The Project Agreement for the installation of traffic signal and sign improvements under the 2011 Highway Safety Improvement Program (HSIP) was approved by the Common Council under File Number 071689; and,

Whereas, The HSIP is intended to reduce the number and severity of vehicle and pedestrian crashes; and

Whereas, The total estimated cost of this project is $113,413.30 for traffic control signal and sign improvements; and

Whereas, Ten percent of the participating costs, or $11,341.33, is not reimbursable and is included in the Division’s 2010 Capital Purpose Project/Grant Numbe...