powered help
header-left header-center header-right
File #: 070266    Version:
Type: Resolution Status: Passed
File created: 5/30/2007 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 6/19/2007
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,467,000 for a total estimated cost of these projects being $18,848,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Infrastructure Services Division Cover Letter.pdf, 2. Fiscal Note
Number
070266
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,467,000 for a total estimated cost of these projects being $18,848,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $1,467,000 with the total cost estimated to be $18,848,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

3rd Aldermanic District

N. Cramer St. - E. Park Pl. to E. Locust St. (SM495070079): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $197,000. This project is anticipated to be completed during the 2008 construction season.

N. Hackett Ave. - E. Newberry Blvd. to E. Kenwood Blvd. (SM495070080): Combined sewer relay and lining. (Nonassessable Sewer Maintenance Relay Fund -- $20,000). The total estimated cost for this project including the requested amount is $430,000. This project is anticipated to be completed during the 2008 construction season.

E. Newberry Blvd. - N. Cramer St. to N. Farwell Ave. (SM495070083): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $200,000. This project is anticipated to be completed during the 2008 construction season.

N. Prospect Ave. - A point 180 feet m/l south of E. Park Pl. to E. Kenwood Blvd. (SM495070...

Click here for full text