powered help
header-left header-center header-right
File #: 221097    Version: 0
Type: Resolution Status: Passed
File created: 11/22/2022 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 1/17/2023
Effective date:    
Title: Resolution directing the Commissioner of Public Works to execute a document titled “State/Municipal Agreement for a State-Let Highway Project” with the Wisconsin Department of Transportation for the programming, design, and construction of West Appleton Avenue (STH 175) from West Lisbon Avenue to West Burleigh Street, and to set up funds for design engineering at an estimated total cost of $600,000 with an estimated City share of $150,000 and a grantor share of $450,000.
Sponsors: THE CHAIR
Indexes: INTERGOVERNMENTAL AGREEMENTS, STREET IMPROVEMENTS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. 2010-05-02-72 STH 175 C MIl Lisbon-Burleigh.pdf, 2. Resolution Certification 2010-05-02.pdf
Number
221097
Version
ORIGINAL
Reference
Sponsor
THE CHAIR
Title
Resolution directing the Commissioner of Public Works to execute a document titled “State/Municipal Agreement for a State-Let Highway Project” with the Wisconsin Department of Transportation for the programming, design, and construction of West Appleton Avenue (STH 175) from West Lisbon Avenue to West Burleigh Street, and to set up funds for design engineering at an estimated total cost of $600,000 with an estimated City share of $150,000 and a grantor share of $450,000.
Analysis
This resolution directs the Commissioner of Public Works to execute a State/Municipal Agreement with the Wisconsin Department of Transportation for the programming, design, and construction of West Appleton Avenue (STH 175) from West Lisbon Avenue to West Burleigh Street. The State/Municipal Agreement provides for 75 percent Federal and State aid and 25 percent local cost sharing for preliminary engineering. The total estimated cost of this project is $8,700,000 with a City share of $318,428 and a grantor share of $8,381,572. This resolution also directs the City Comptroller to transfer funds for preliminary engineering at an estimated cost of $600,000 with an estimated City share of $150,000 and a grantor share of $450,000. Construction funds for this project will be included in future resolutions.
Body
Whereas, A project agreement has been requested and received from the Wisconsin Department of Transportation (WisDOT) to be executed by the City of Milwaukee for the programming, design, and construction of West Appleton Avenue (STH 175) from West Lisbon Avenue to West Burleigh Street with Federal and State aid under the State Highway Rehabilitation Program; and

Whereas, The Department of Public Works shall notify the Common Council of the City of Milwaukee of project cost overruns and changes in scope approved by the Department of Public Works; and

Whereas, The Common Council of the City of Milwaukee re...

Click here for full text