File #: 111283    Version:
Type: Resolution Status: Passed
File created: 1/18/2012 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 2/7/2012
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $11,544,000 for a total estimated cost of these projects being $11,691,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SANITARY SEWERS, SEWER IMPROVEMENTS
Attachments: 1. Hearing Notice List
Number
111283
Version
Substitute 1
Reference
100723
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $11,544,000 for a total estimated cost of these projects being $11,691,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $11,544,000. The total estimated cost of these projects is $11,691,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

1st Aldermanic District

N. 19th St. - W. Capitol Dr. to W. Fiebrantz Ave. (SM495100208) File Number 100723: Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $119,000). The total estimated cost for this project including the requested amount is $134,000. This project is anticipated to be completed during the 2012 construction season.

1st and 6th Aldermanic Districts

W. Atkinson Ave. - W. Capitol Dr. to N. 20th St. (SM495110071) File Number 111024: Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $66,000). The total estimated cost for this project including the requested amount is $78,000. This project is anticipated to be completed during the 2012 construction season.

W. Capitol Dr. (south side) - N. 19th Pl. to N. 21st St. (SM495110077) File Number 111024: Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $97,000). The total estimated cost for this project including the requested amount is $112,000. This proje...

Click here for full text