powered help
header-left header-center header-right
File #: 130040    Version:
Type: Resolution Status: Passed
File created: 4/30/2013 In control: COMMON COUNCIL
On agenda: Final action: 5/21/2013
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $460,400 for a total estimated cost of $508,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SPECIAL ASSESSMENTS
Attachments: 1. Official Notice Number 1 Committee Actions, 2. Official Notice Number 1, 3. Cover Letter, 4. Hearing Notice List, 5. Notice Published on 6-10-13
Number
130040
Version
SUBSTITUTE 1
Reference
110352
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $460,400 for a total estimated cost of $508,000.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $460,400. The total estimated cost of these projects is $508,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

3rd and 6th Aldermanic Districts

E. North Ave. - N. Humboldt Blvd. to N. Bremen St. (ST211130114) File Number 110352: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding, and grading. (Assessable Reconstruction Paving Fund -- $5,200; Nonassessable Reconstruction Paving Fund -- $95,000). The total estimated cost for this project including the requested amount is $110,000. This project is anticipated to be completed during the 2013-2014 construction season.

10th Aldermanic District

W. Townsend St. - N. 54th St. to N. 57th St. (ST211120143) File Number 091621: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (8-foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $7,700; Nonassessable Reconstruction Paving Fund -- $175,000). The total esti...

Click here for full text