powered help
header-left header-center header-right
File #: 001764    Version:
Type: Resolution Status: Passed
File created: 4/10/2001 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 5/8/2001
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations.
Sponsors: THE CHAIR
Indexes: ALLEY IMPROVEMENTS, PUBLIC IMPROVEMENTS, RIVERWALKS, SEWER IMPROVEMENTS, SEWERS, SIDEWALKS, SPECIAL ASSESSMENTS, STORM SEWERS, STREET IMPROVEMENTS
Attachments: 1. FISCAL NOTE.pdf
 
Number
001764
Version
SUBSTITUTE 1
Reference
991843
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held.  The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:
 
1st Aldermanic District
 
W. Congress St. - N. Green Bay Ave. to N. 19th Pl. (ST211010148) File Number 991843:  Asphalt pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where needed, sodding, and grading. (Assessable Reconstruction Paving Fund -- $134,100; Nonassessable Reconstruction Paving Fund -- $263,000)
 
4th Aldermanic District
 
Alley between N. Broadway, E. Buffalo St., E. Chicago St. and N. Milwaukee St. (ST21210123) File Number 991032:  Concrete alley pavement reconstruction, replace some abutting sidewalk or driveway approach. (Assessable Alley Paving Fund -- $25,300; Nonassessable Alley Paving Fund -- $8,900)
 
6th Aldermanic District
 
N. Cape St. - E. Vine St. to E. Ship St. (TD02284019) File Number 001347:  Concrete pavement construction, place curb and gutter, sidewalk and driveway approaches, sodding, and grading. (Assessable New Paving Fund -- $16,900; TID 22 Funds -- $3,800)
 
E. Dock St. - The Milwaukee River to N. Commerce St. (TD02284019) File Number 001347:  Concrete pavement construction, place curb and gutter, sidewalk and driveway approaches, sodding, and grading. (Assessable New Paving Fund -- $29,400; TID 22 Funds -- $12,400)
 
River Homes Development: N. Booth St., N. Pierce St., N. Fratney St., and N. Weil St. (TD02284001) File Number 001765:  Riverwalk construction. (TID 22 Funds -- $383,000)
 
E. Ship St. - The Milwaukee River to N. Commerce St. (TD02284019) File Number 001347:  Concrete pavement construction, place curb and gutter, sidewalk and driveway approaches, sodding, and grading. (Assessable New Paving Fund -- $28,100; TID 22 Funds -- $31,800)
 
Trostel Development: N. Cape St., E. Ship St., E. Vine St. (TD02284019) File Number 001668:  Install water main. (Assessable Water Fund -- $52,500; TID 22 Funds  -- $127,600)
 
Trostel Development: N. Cape St., E. Ship St., E. Vine St. (TD02284019) File Number 001765:  Install storm sewer. (Assessable Expansion of Capacity Sewer Fund -- $63,400; TID 22 Funds  -- $74,700)
 
Trostel Development: E. Vine St., E. Ship St., E. Dock St. (TD02284019) File Number 001765:  Riverwalk construction. (TID 22 Funds -- $337,200)
 
E. Vine St. - The Milwaukee River to N. Commerce St. (TD02284019) File Number 001347:  Concrete pavement construction, place curb and gutter, sidewalk and driveway approaches, sodding, and grading. (Assessable New Paving Fund -- $28,600; TID 22 Funds -- $37,100)
 
Alley between W. Center St., W. Christine Ln., N. Dr. Martin Luther King. Jr. Dr., and N. 4th St. (ST21210107) File Number 941871:  Concrete alley pavement reconstruction, replace some abutting sidewalk or driveway approach. (Assessable Alley Paving Fund -- $27,200; Nonassessable Alley Paving Fund -- $9,700)
 
Alley between W. Center St., W. Clarke St., N. Dr. Martin Luther King. Jr. Dr., and N. 4th St. (ST21210108) File Number 941197:  Concrete alley pavement reconstruction, replace some abutting sidewalk or driveway approach. (Assessable Alley Paving Fund -- $57,600; Nonassessable Alley Paving Fund -- $16,100)
 
Alley between N. Commerce St., E. Dock St., E. Ship St. and the Milwaukee River (TD02284019) File Number 001347:  Concrete alley pavement construction, place sidewalk and driveway approach. (Assessable Alley Paving Fund -- $10,600; TID 22 Funds -- $3,000)
 
Alley between N. Commerce St., E. Pleasant St., E. Vine St. and The Milwaukee River: (TD02284019) File Number 001347:  Concrete alley pavement construction, place sidewalk and driveway approach. (Assessable Alley Paving Fund -- $10,100; TID 22 Funds -- $3,500)
 
8th Aldermanic District
 
Alley between W. Becher St., S. Layton Bl., W. Rogers St. and S. 26th St. (ST212010148) File Number 000616:  Concrete alley pavement reconstruction, replace some abutting sidewalk or driveway approach. (Assessable Alley Paving Fund -- $50,300; Nonassessable Alley Paving Fund -- $36,600)
 
16th Aldermanic District
 
W. Wells St. (Sponsored by Wauwatosa) - N. Hawley Rd. to a point west of N. Hawley Rd. (ST211010168) File Number 001534:  Asphalt pavement resurfacing, replace all curb and gutter, replace sidewalk and driveway approaches where needed, sodding, and grading. (Assessable Reconstruction Paving Fund -- $3,800; Nonassessable Reconstruction Paving Fund -- $7,600)
 
;and
 
Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and
 
Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it
 
Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works' Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it
 
Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.60 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
 
Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances, and, be it
 
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it
 
Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it
 
Further Resolved, That projects W. Congress St. (ST211010148), Alley N. Broadway (ST21210123), N. Cape St. (TD02284019), E. Dock St. (TD02284019), River Homes Development (TD02284001), E. Ship St. (TD02284019), Trostel Development (Water Main) (TD02284019), Trostel Development (Storm Sewer) (TD02284019), Trostel Development (Riverwalk) (TD02284019), E. Vine St. (TD02284019), Alley W. Center St. (ST21210107), Alley W. Center St. (ST21210108), Alley N. Commerce St. (TD02284019), Alley N. Commerce St. (TD02284019), Alley W. Becher St. (ST212010148), and W. Wells St. (ST211010168) will be billed after January 1, 2003, but not before 12 months after the project contract has been completed.
 
Requestor
Infrastructure Services Division
Drafter
mld:lk
afr11
04/25/01