File #: 231570    Version:
Type: Resolution Status: Passed
File created: 2/6/2024 In control: COMMON COUNCIL
On agenda: Final action: 2/27/2024
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $1,297,594 for a total estimated cost of these projects being $2,110,139.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Resolution Certification 2984-22-75.pdf

Number

231570

 

Version

SUBSTITUTE 1

 

Reference

201243

 

Sponsor

THE CHAIR

 

Title

Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $1,297,594 for a total estimated cost of these projects being $2,110,139.

 

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $1,297,594.  The total estimated cost of these projects is $2,110,139.

 

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

1st Aldermanic District

 

 20th St Power Line and Beerline Trail - Olive St to Villard Ave & 24th St to 20th St. (ST3202102XX) (2984-22-75) File Number 201243: Construct a 10-foot wide shared use asphalt trail on the WE Energies power line corridor parallel to North 20th Street between West Olive Street and West Villard Avenue and on the former Beerline rail corridor between North 24th Place and North 20th Street.  This project is anticipated to be completed in the 2024 construction season.

 

Grantor Non-Reimbursable Fund -- $674,374

City Share Non-Assessable Fund -- $168,594

 

These funds are to be transferred to the construction account (ST3202102XX) (2984-22-75)

 

Previously authorized for project construction: $0.00

Current estimated cost of construction including the resolution: $842,968

Current estimated total cost of the project including this resolution: $981,139

Original estimated cost of the project: (File Number 201243): $981,139

 

1st and 4th Aldermanic District

 

2024 N. 27th St. And W. Highland Ave. Bioretention Maintenance (SM499240003) Bioretention maintenance. (Nonassessable Water Quality Fund -- $50,000). The total estimated cost of this project including the requested amount is $50,000. This project is anticipated to be completed during the 2024 construction season.

 

4th Aldermanic District

 

2024 Overpass Green Infrastructure Maintenance (SM499240020) Green Infrastructure maintenance. (Nonassessable Water Quality Fund -- $50,000). The total estimated cost of this project including the requested amount is $50,000. This project is anticipated to be completed during the 2024 construction season.

 

4th, 8th and 12th Aldermanic Districts

 

16th Street Viaduct over the Menomonee River Stair Replacement (BR100240109): (City Share Non-assessable Structure Fund - $500,000).  The total estimated cost for this project is $500,000. This project is anticipated to be completed during the 2024 construction season.

 

7th and 15th Aldermanic District

 

2024 N. Sherman Blvd. Bioretention Maintenance (SM499240004) Bioretention maintenance. (Nonassessable Water Quality Fund -- $50,000). The total estimated cost of this project including the requested amount is $50,000. This project is anticipated to be completed during the 2024 construction season.

 

10th Aldermanic District

 

2024 Wisconsin Viaduct Vegetation Management and Monitoring (SM499240005) Vegetation maintenance. (Nonassessable Water Quality Fund -- $10,000). The total estimated cost of this project including the requested amount is $10,000. This project is anticipated to be completed during the 2024 construction season.

 

Citywide

 

2024 Northside Bioretention Maintenance (SM499240001) Bioretention maintenance. (Nonassessable Water Quality Fund -- $312,000). The total estimated cost of this project including the requested amount is $312,000. This project is anticipated to be completed during the 2024 construction season.

 

2024 Southside Bioretention Maintenance (SM499240002) Bioretention maintenance. (Nonassessable Water Quality Fund -- $157,000). The total estimated cost of this project including the requested amount is $157,000. This project is anticipated to be completed during the 2024 construction season.

 

now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

 

Drafter

Holly Rutenbeck

NFR 8 Sub

2/9/2024