powered help
header-left header-center header-right
File #: 201669    Version:
Type: Resolution Status: Passed
File created: 4/13/2021 In control: COMMON COUNCIL
On agenda: Final action: 5/4/2021
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $327,000 for a total estimated cost of these projects being $4,426,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

Number

201669

Version

Substitute 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $327,000 for a total estimated cost of these projects being $4,426,000.

Analysis

This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $327,000 with the total cost estimated to be $4,426,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

 

2nd Aldermanic District

 

W. Capitol Dr. - N. 51st Blvd. to N. 52nd St. (SM495210029) Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost of this project including the requested amount is $75,000.  This project is anticipated to be completed during the 2021 construction season.

 

5th Aldermanic District

 

W. Appleton Pl. - N. 115th St. to W. Appleton Ave. (WT410220713) Water main extension. (Nonassessable Water Fund Budget Line 5010 -- $1,000; Nonassessable Water Fund Budget Line 6410 -- $19,000). The total estimated cost of this project including the requested amount is $295,000.  This project is anticipated to be completed during the 2022 construction season.

 

N. 115th St. -  W. Appleton Pl. to W. Green Tree Rd. (WT410220712) Water main extension. (Nonassessable Water Fund Budget Line 5010 -- $1,000; Nonassessable Water Fund Budget Line 6410 -- $19,000).  The total estimated cost of this project including the requested amount is $225,000.  This project is anticipated to be completed during the 2022 construction season.

 

6th Aldermanic District

 

W. Abert Pl. - N. 3rd St. to 200’ west of N. 3rd St. (SM495210028)  Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost of this project including the requested amount is $71,000.  This project is anticipated to be completed during the 2021 construction season.

 

Alley +/- 125' east of  N. 6th  St  -. W. McKinley Ave. to 110' +/- north of

W.  McKinley Ave.  (SM495210032) Combined Relay (Nonassessable Sewer Maintenance relay fund -- $10,000).   The total estimated cost of this project is $48,000.  This project is anticipated to be completed during the 2022 construction season.

 

11th Aldermanic District

 

S. Athens St. - W. New Jersey Ave. to W. Crawford Ave.  (SM495210019) Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $155,000.  This project is anticipated to be completed during the 2021 construction season.

 

W. Nebraska Ave. - S. 61st St. to S. 63rd St. (SM495210020)  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $256,000.  This project is anticipated to be completed during the 2021 construction season.

 

W. New Jersey Ave. - S. 81st St. to S. 83rd St. (SM495210018) Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $123,000.  This project is anticipated to be completed during the 2021 construction season.

 

W. Tripoli Ave. - S. 85th St. to S. 87th St. (SM495210021) Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $159,000.  This project is anticipated to be completed during the 2021 construction season.

 

Area bounded by W. Warnimont Ave., W. Wilbur Ave., S. 85th St. and  S. 87th St. (SM495210030) Building Sanitary Sewer Rehabilitation   (Nonassessable Sewer Maintenance Relay Fund--, $50,000). The total estimated cost of this project including the requested amount is $555,000.  This project is anticipated to be completed during the 2021 construction season.

 

W. Warnimont Ave. - S. 84th St. to S. 87th (SM495210026)  Installing new storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost of this project including the requested amount is $388,000.  This project is anticipated to be completed during the 2021 construction season.

 

S. 40th St.-W. Oklahoma Ave. to W. Euclid Ave. (SM495210027)  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $174,000.  This project is anticipated to be completed during the 2021 construction season.

 

S. 81st St. - W. Morgan Ave. to W. Warnimont Ave. (SM495210016) Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $165,000.  This project is anticipated to be completed during the 2021 construction season.

 

S. 83rd St. - W. Wilbur Ave. to W. New Jersey Ave. (SM495210017)  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost of this project including the requested amount is $60,000.  This project is anticipated to be completed during the 2021 construction season.

 

S. 85th St. -- W. Warnimont Ave. to 350’ south of W. Warnimont Ave.  (SM495210025) Installing new storm sewer and Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $123,000.  This project is anticipated to be completed during the 2021 construction season.

 

S. 85th St. - W. Warnimont Ave. to W. Wilbur Ave. (SM495210022) Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $171,000.  This project is anticipated to be completed during the 2021 construction season.

 

S. 86th St. - W. Warnimont Ave. to 300’ south of Warnimont Ave. (SM495210024) Installing new storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $119,000.  This project is anticipated to be completed during the 2021 construction season.

 

S. 87th St. - W. Warnimont Ave. to 300’ south of Warnimont Ave. (SM495210023) Installing new storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $119,000.  This project is anticipated to be completed during the 2021 construction season.

 

13th Aldermanic District

 

S. 20th St. - W. Grange Ave. to W. Klein Ave. (WT410220714) Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $1,000; Nonassessable Water Fund Budget Line 6410 -- $19,000).  The total estimated cost of this project including the requested amount is $275,000.  This project is anticipated to be completed during the 2022 construction season.

 

S. 20th St. - W. Klein Ave. to W. Ramsey Ave. (WT410220715) Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $1,000; Nonassessable Water Fund Budget Line 6410 -- $24,000).  The total estimated cost of this project including the requested amount is $370,000.  This project is anticipated to be completed during the 2022 construction season.

 

City Wide

Permanent Pavement Replacement at Various Locations (SM495210031)

(Sewer Maintenance Relay Fund - Nonassessable -- $15,000).

The total estimated cost of this project is $500,000.  This project is anticipated to be completed during the 2021 construction season.

 

;and, be it

 

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/dl

Npr 11 Sub

04/06/2021