File #: 210701    Version:
Type: Resolution Status: Passed
File created: 9/1/2021 In control: COMMON COUNCIL
On agenda: Final action: 9/21/2021
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $500,000 for a total estimated cost of these projects being $6,984,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
9/22/20211 MAYOR SIGNED   Action details Meeting details Not available
9/21/20211 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Video Video
9/9/20210 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Proposed Substitute A
Pass5:0 Action details Meeting details Video Video
9/9/20211 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Mary Dziewiontkoski - DPW
Pass5:0 Action details Meeting details Video Video
9/1/20210 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

 

Number

210701

Version

Substitute 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $500,000 for a total estimated cost of these projects being $6,984,000.

Analysis

This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $500,000 with the total cost estimated to be $6,984,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

 

1st Aldermanic District

 

N. 25th St. - 125’ +/- north of W. Capitol Dr. to W. Hope Ave. (SM495210054) Relaying storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000).   The total estimated cost of this project is $232,000. This project is anticipated to be completed during the 2022 construction season. 

 

2nd Aldermanic District

 

W. Medford Ave. - W. Custer Ave. to W. Sheridan Ave. (SM495210044) Sanitary Sewer Lining.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost of this project including the requested amount is $62,000.  This project is anticipated to be completed during the 2022 construction season. 

 

3rd Aldermanic District

 

Sewer Easement - E. Kenwood Blvd. 770’ +/- east of N. Lake Dr. to E. Hampshire St. 735’ +/- east of N. Lake Dr.  (SM495210040) Relaying Sanitary and Storm Sewers.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $106,000.  This project is anticipated to be completed during the 2021 construction season. 

 

E. Locust St. - N. Humboldt Ave. to N. Dousman St.  (WT410220716)  Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $1,000; Nonassessable Water Fund Budget Line 6410 -- $14,000). The total estimated cost of this project including the requested amount is $115,000.  This project is anticipated to be completed during the 2022 construction season.

 

3rd Aldermanic District

 

E. Meinecke Ave. - N. Dousman St. to N. Gordon Pl. (SM495210047) Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $95,000.  This project is anticipated to be completed during the 2022 construction season. 

 

4th Aldermanic District

 

N. 34th St. - 235’ +/- south of W. Wells St. to W. Wells St. (SM495210055) Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $79,000.  This project is anticipated to be completed during the 2022 construction season. 

 

5th Aldermanic District

 

W. Appleton Ave. - N. 76th St. to W. Hope Ave. (SM495210039) Relaying Sanitary and Storm Sewers.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $155,000.  This project is anticipated to be completed during the 2022 construction season.

 

6th Aldermanic District

 

E. Auer Ave. - N. Richards St. to N. Buffum St. (SM495210046) Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $95,000.  This project is anticipated to be completed during the 2022 construction season. 

 

W. Chambers St. - 345’ +/- east of W. Hopkins St. to 170’ +/- east of W. Hopkins St. (SM495210050)  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost of this project including the requested amount is $58,000.  This project is anticipated to be completed during the 2022 construction season. 

 

7th Aldermanic District

 

W. Cawker Pl. - N. 30th St. to 360’ +/- west of N. 30th St.  (SM495210048) Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost of this project including the requested amount is $59,000.  This project is anticipated to be completed during the 2022 construction season. 

W. Chambers St. - N. 37th St. to 135’ +/- west of N. 39th St. (SM495210049) Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $178,000.  This project is anticipated to be completed during the 2022 construction season. 

 

W. Locust St. - N. 35th St. to 140’+/- west of N. 36th St. (SM495210041) Relaying Combined Sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $75,000.  This project is anticipated to be completed during the 2022 construction season.

 

8th Aldermanic District

 

S. 28th St. - 260’ north of W. Rogers St. to W. Rogers St. (SM495210045) (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $78,000.  This project is anticipated to be completed during the 2022 construction season.

 

S. 29th St. - W. Forest Home Ave. to W. Cleveland Ave. (SM495210058) Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost of this project including the requested amount is $369,000.  This project is anticipated to be completed during the 2022 construction season. 

 

10th Aldermanic District

 

W. Cherry St. - N. 47th St. to N. 48th St. (SM495210060) Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $99,000.  This project is anticipated to be completed during the 2022 construction season. 

 

N. 51st. St. -- 245’ +/- south of W. Lloyd St. to W. Lloyd St. (SM495210056) Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $85,000.  This project is anticipated to be completed during the 2022 construction season. 

 

11th Aldermanic District

 

S. 81st St.-330’ north of W. Ohio Ave. to W. Ohio Ave. (SM495210043) Relaying Sanitary and Storm Sewers.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $89,000.  This project is anticipated to be completed during the 2022 construction season. 

 

S. 85th St. - W. Ohio Ave.to 100’ +/- south of W. Holt Ave. (SM495210042) Relaying Sanitary and Storm Sewers (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $187,000.  This project is anticipated to be completed during the 2022 construction season. 

 

12th Aldermanic District

 

W. Madison St. - S. 3rd St. to S. 4th St. (SM495210052) Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost of this project including the requested amount is $39,000.  This project is anticipated to be completed during the 2022 construction season. 

 

W. Washington St. - S. 1st St. to S. 20th St., W. Scott St. - S. 20th St. to S. Layton Blvd.(ST216210110) Asphalt surface overlay: replace ADA ramps as necessary (Nonassessable High Impact Paving Fund -- $50,000).  The total estimated cost of this project including the requested amount is $750,000.  This project is anticipated to be completed during the 2022-2023 construction season.

 

15th Aldermanic District 

 

W. Clarke St. - N. 37th St. to N. 38th St. (SM495210051) Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $75,000.  This project is anticipated to be completed during the 2022 construction season. 

 

N. Grant Blvd. - W. North Ave. to W. Clarke St. (SM495210062) Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $20,000).  The total estimated cost of this project including the requested amount is $868,000.  This project is anticipated to be completed during the 2022 construction season. 

 

W. Oak St. - N. 23rd St./ W. Fond du Lac Ave. to N. 24th St. / W. Medford Ave.  (SM495210053) Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost of this project including the requested amount is $122,000.  This project is anticipated to be completed during the 2022 construction season. 

 

N. 40th St. - W. Meinecke Ave. to W. Wright St. (SM495210061) Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost of this project including the requested amount is $494,000.  This project is anticipated to be completed during the 2022 construction season. 

 

N. 44th St. - W. Meinecke Ave. to W. Clarke St. (SM495 210059) Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost of this project including the requested amount is $420,000.  This project is anticipated to be completed during the 2022 construction season. 

 

City Wide

 

ADA ramps for 2022 High impact paving north-side projects: (ST216210111) Replace curb and gutter and sidewalk as necessary (Nonassessable High Impact Paving Fund - $75,000).  The total estimated cost of this project including the requested amount is $1,000,000.  This project is anticipated to be completed during the 2022 construction season. 

 

ADA ramps for 2022 High impact paving south-side projects: (ST216210112) Replace curb and gutter and sidewalk as necessary (Nonassessable High Impact Paving Fund -- $75,000).  The total estimated cost of this project including the requested amount is $1,000,000.  This project is anticipated to be completed during the 2022 construction season.

 

;and, be it

 

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/dl

Npr1 sub

09/01/2021