powered help
header-left header-center header-right
File #: 170479    Version:
Type: Resolution Status: Passed
File created: 7/11/2017 In control: COMMON COUNCIL
On agenda: Final action: 7/31/2017
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $84,000 for a total estimated cost of these projects being $766,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

Number

170479

Version

Substitute 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $84,000 for a total estimated cost of these projects being $766,000.

Analysis

This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $84,000 with the total cost estimated to be $766,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

 

2nd and 9th Aldermanic District

 

West Mill Road Bioswales:  W. Mill Rd. - N. 43rd St. to N. 91st St. (SM499160121):  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $15,000, Additional Funds).  The total estimated cost for this project including the requested amount is $400,000.  This project is anticipated to be completed during the 2017 construction season.

 

4th Aldermanic District

 

E./W. Wells St. - N. Broadway to N. 6th St. (WT410180009):  Hydrant alterations.  (Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $13,000).  The total estimated cost for this project including the requested amount is $40,000.  This project is anticipated to be completed during the 2018 construction season.

 

7th Aldermanic District

 

N. 35th St. - 200 feet south of W. Capitol Dr. to W. Capitol Dr. (SM494170014):  Relaying sanitary sewer.  (Infiltration/Inflow Reduction Fund -- $ 12,000).  The total estimated cost for this project including the requested amount is $91,000.  This project is anticipated to be completed during the 2018 construction season.

 

11th Aldermanic District

 

W. Cleveland Ave. - W. Kinnickinnic River Pkwy. to S. 67th St. (SM495170048):  Sanitary Sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $112,000.  This project is anticipated to be completed during the 2018 construction season.

 

13th Aldermanic District

 

System 2413 Outfall - 350 feet east of S. 20th St. to The Kinnickinnic River (SM499170108):  (Nonassessable Storm Water Quality Fund -- $10,000).  The total estimated cost for this project including the requested amount is $39,000.  This project is anticipated to be completed during the 2017 construction season.

 

15th Aldermanic District

 

N. Sherman Bd. (east side) - W. Wright St. to W. Clarke St. (SM495170049):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $49,000.  This project is anticipated to be completed during the 2018 construction season.

 

N. 18th St. - 115 feet south of W. Galena St. to W. Galena St. (SM495170050):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $35,000.  This project is anticipated to be completed during the 2018 construction season.

 

;and, be it

 

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/Jean Ziller

Npr 15

07/14/2017