File #: 230604    Version: 0
Type: Resolution Status: Passed
File created: 9/1/2023 In control: COMMON COUNCIL
On agenda: Final action: 9/19/2023
Effective date:    
Title: Resolution directing the Commissioner of Public Works to execute two documents titled “Cost Sharing Memo of Understanding Between the City of Milwaukee and the City of Greenfield” for the design, construction, and construction engineering of the Powerline Trail Phase 2 project.
Sponsors: ALD. SPIKER
Indexes: GREEN SPACE, INTERGOVERNMENTAL AGREEMENTS
Attachments: 1. Cost Sharing Agreement Powerline Ph 2 Construction-FINAL.pdf, 2. Cost Sharing Agreement Powerline Ph 2 Design-FINAL.pdf, 3. Resolution Comptroller's Certification 2980-22-70, 4. Resolution Comptroller's Certification 2980-22-00
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
9/28/20230 MAYOR SIGNED   Action details Meeting details Not available
9/19/20230 COMMON COUNCIL ADOPTED

Minutes note: Ald. Spiker added as the sponsor.
Pass14:0 Action details Meeting details Video Video
9/7/20230 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Kate Riordan - DPW
Pass5:0 Action details Meeting details Video Video
9/1/20230 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

230604

Version

 

Reference

190517

Sponsor

ALD. SPIKER

Title

Resolution directing the Commissioner of Public Works to execute two documents titled “Cost Sharing Memo of Understanding Between the City of Milwaukee and the City of Greenfield” for the design, construction, and construction engineering of the Powerline Trail Phase 2 project.

Analysis

This resolution directs the Commissioner of Public Works to execute two documents titled “Cost Sharing Memo of Understanding Between the City of Milwaukee and the City of Greenfield” for the cost sharing of the design, construction, and construction engineering of the Powerline Trail Phase 2 from S. 51st Street to S. 35th Street (Greenfield) and S. 60th Street to S. 51st Street (Milwaukee) in the 11th Aldermanic District with a total estimated cost of the project to be $1,233,258, with a grantor share of $1,055,492, and a local of $147,538, of which the City’s share is $39,836 and the City of Greenfield’s share is $107,702.

 

Body

Whereas, The City of Greenfield and the City of Milwaukee received grant funds from the Wisconsin Department of Transportation’s (WisDOT) Congestion Mitigation and Air Quality (CMAQ) grant program (WisDOT Project ID 2980-22-00/70) and the Wisconsin Department of Natural Resource’s Recreation Funding (WDNR Project Number SADLP3221385); and

 

Whereas, The Department of Public Works shall notify the Common Council of the City of Milwaukee of project cost overruns and changes in scope approved by the Department of Public Works; and

 

Whereas, The Common Council of the City of Milwaukee recognizes that the City may be 100 percent liable for project cost overruns and changes in scope as approved by the Department of Public Works; and

 

Whereas, the City of Greenfield has constructed the Powerline Trail from S. 104th Street to South 60th Street; and

 

Whereas, The 2010 Milwaukee by Bike Plan recommended the South Side Powerline Trail as a proposed new off-street trail; and

 

Whereas, The WE Energies right-of-way upon which the trail will be built is within the City of Milwaukee boundaries between S. 60th Street to S. 51st Street; and

 

Whereas, The City of Greenfield will be the lead agency of the project design; and

 

Whereas, This project is expected to be constructed in 2024; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public works is hereby authorized to execute the two documents titled “Cost Sharing Memo of Understanding Between the City of Milwaukee and the City of Greenfield” for the cost sharing of the design, construction, and construction engineering of the Powerline Trail Phase 2 from S. 51st Street to S. 35th Street (Greenfield) and S. 60th Street to S. 51st Street (Milwaukee with a copy of which is attached to Common Council Resolution File Number ___ , and is incorporated by reference as though set forth in full; and, be it

 

Further Resolved, That the City Comptroller is hereby authorized to create within the Capital Improvement Fund, Grant and Aid Projects, the necessary Project Grant Chartfield Values for design, construction, and procurement for the project (Expenditure) and transfer to any of these accounts the amount required under the grant agreement and City Accounting Policy but not to exceed a 10 percent increase of the total amounts reserved for the grantor’s share and local share or $5,000, whichever is greater, as follows:

 

Project I.D. 2980-22-00

Powerline Trail Phase 2

South 51st Street to South 35th Street and South 60th Street to South 51st Street.

 

Design

 

City Share Non-Assessable Fund

ST320230000

Fund 0333

$22,989

 

City of Greenfield $62,153

 

Grantor Non-Reimbursable $92,624

 

Project I.D. 2980-22-70

Powerline Trail Phase 2

South 51st Street to South 35th Street and South 60th Street to South 51st Street.

 

Construction and Construction Engineering

 

City Share Non-Assessable Fund

ST320230000

Fund 0333

$16,847

 

City of Greenfield $45,549

 

Grantor Non-Reimbursable $993,096

 

 

Estimated Total Design $177,766

Estimated Total Construction and Construction Engineering $1,055,492

Total Previously Authorized $0

Current Estimated Cost of the Project Including this Resolution $1,233,258

Original Estimated Cost of the Project including this Resolution $1,233,258

 

Requestor

Department of Public Works

Drafter

Infrastructure Services Division

Kate Riordan/Mike Amsden/S. Leavy

August 22, 2023