powered help
header-left header-center header-right
File #: 231267    Version: 0
Type: Resolution Status: Passed
File created: 12/12/2023 In control: COMMON COUNCIL
On agenda: Final action: 1/17/2024
Effective date:    
Title: Resolution directing the Commissioner of Public Works to execute a document titled “1st Revision State/Municipal Agreement for a State-Let Highway Project” with the Wisconsin Department of Transportation for the programming, design, real estate acquisition, and construction of North Mayfair Road/Lovers Lane (STH 100) from West Burleigh to West Silver Spring.
Sponsors: THE CHAIR
Indexes: INTERGOVERNMENTAL AGREEMENTS, STREET IMPROVEMENTS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Comptroller's Resolution Certification, 2. State Municipal Financial Agreement

Number

231267

Version

ORIGINAL

Reference

Sponsor

THE CHAIR

Title

Resolution directing the Commissioner of Public Works to execute a document titled “1st Revision State/Municipal Agreement for a State-Let Highway Project” with the Wisconsin Department of Transportation for the programming, design, real estate acquisition, and construction of North Mayfair Road/Lovers Lane (STH 100) from West Burleigh to West Silver Spring. 

Analysis

This resolution directs the Commissioner of Public Works to execute a revised State/Municipal Agreement with the Wisconsin Department of Transportation for the programming, design, real estate acquisition, and construction of North Mayfair Road/Lovers Lane (STH 100) from West Burleigh to West Silver Spring.  The revised total estimated cost of this project is $18,220,250 with a grantor share of $18,037,150 and a City share of $183,100. 

Body

Whereas, A revised project agreement has been requested and received from the Wisconsin Department of Transportation (WisDOT) to be executed by the City of Milwaukee for the programming, design, real estate acquisition, and construction of North Mayfair Road/Lovers Lane (STH 100) from West Burleigh to West Silver Spring with Federal and State aid under the State Highway Rehabilitation Program; and

 

Whereas, The Department of Public Works shall notify the Common Council of the City of Milwaukee of project cost overruns and changes in scope approved by the Department of Public Works; and

 

Whereas, The Common Council of the City of Milwaukee recognizes that the City may be 100 percent liable for project cost overruns and changes in scope as approved by the Department of Public Works; and

 

Whereas, The Common Council of the City of Milwaukee recognizes that the City may be liable for any cost incurred by the State should the City decide to withdraw from the project; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is hereby authorized to execute the revised agreement for the programming, design, real estate acquisition, and construction of the aforementioned connecting highway project with Federal and/or State aid, copies of which are attached to Common Council Resolution File Number 231267, and are incorporated into this resolution by reference as though set forth in full; and, be it

 

Further Resolved, That the Commissioner of Public Works is hereby authorized to undertake or engage a consultant to undertake preliminary engineering for the improvement of the aforementioned project and to reimburse the WisDOT for preliminary engineering costs they incur from the improvement; and, be it

 

Further Resolved, That the City Comptroller is hereby authorized to create within the Capital Improvement Fund, Grant and Aid Projects, the necessary Project Grant Chartfield Values for design engineering for the project (Expenditure) and transfer to any of these accounts the amount required under the grant agreement and City Accounting Policy but not to exceed a 10 percent increase of the total amounts reserved for the grantor’s share and local share or $5,000, whichever is greater, as follows:

 

State I.D. 2030-10-71

ST320210710

North Mayfair Road/Lovers Lane (STH 100) from West Burleigh to West Silver Spring

 

City Share

ST320230000

Fund 0333

$95,100

 

Grantor Reimbursable Funds

SP032230100

Fund 0306

$0

 

Grantor Non-Reimbursable Funds

$(158,100)

 

Estimated Total Construction $(63,000)

Total Construction Previously Authorized $16,824,750

Current Estimated Cost of Total Project Including this Resolution $18,220,250

Original Estimate Cost of Total Project (Resolution File Number 210432) $18,283,250

 

Further Resolved, That the City Engineer is hereby authorized to approve and make periodic payments to the WisDOT upon receipt of invoices for the City’s share of the project costs.

Requestor

Department of Public Works

Drafter

Infrastructure Services Division

DAVID J TAPIA:K. Vos

December 4, 2023