File #: R13472    Version: 0
Type: Housing Authority Resolution Status: Passed
File created: 4/4/2024 In control: HOUSING AUTHORITY
On agenda: 4/10/2024 Final action: 4/10/2024
Effective date:    
Title: Resolution approving an award of contract to Hurt Electric Inc. (Wauwatosa, WI) for electrical for single-family market-rate townhomes Phase 5C-1 at Westlawn Gardens Phase 2 in the amount of $317,000 (Official Notice 58122)
Sponsors: THE CHAIR
Attachments: 1. Bid Tab 58122 Hurt Electric WLG Ph2 Electrical, 2. Schedule of Values Hurt Electric Inc.
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
4/10/20240 HOUSING AUTHORITY ADOPTED

Minutes note: Warren Jones, Travaux, Inc.’s, Vice President of Construction, stated that staff is recommending awarding Hurt Electric Inc. (Wauwatosa, WI) the contract for electrical work at the Westlawn Gardens Phase 2 site. Mr. Jones noted that Hurt Electric has performed very satisfactorily for HACM in similar work in the past. He also stated that the bid came in about $90,000 below the estimated budget amount. The bid was vetted to the scope of work to make sure that all the work was included in the bid amount, and it was found to be sufficient. Hurt Electric is a certified Minority Business Enterprise with the State of Wisconsin and has not identified a need to subcontract or hire at this time.
Pass3:0 Action details Meeting details Not available

Number

13472

 

Version

Original

 

Reference

 

Sponsor

The Chair

 

Title

Resolution approving an award of contract to Hurt Electric Inc. (Wauwatosa, WI) for electrical for single-family market-rate townhomes Phase 5C-1 at Westlawn Gardens Phase 2 in the amount of $317,000 (Official Notice 58122)

Analysis

 

Body

WHEREAS, the Housing Authority of the City of Milwaukee (Housing Authority) solicited sealed bids by Official Notice Number 58122 during the period January 26, 2024 through February 23, 2024 for Electrical for Single-Family Market-Rate Townhomes Phase 5C-1 at Westlawn Gardens Phase 2; and

 

WHEREAS, two (2) sealed bids were received by the deadline of 2:00 (CST) on February 23, 2024; and

 

WHEREAS, the sealed bids were received and publicly opened on February 23, 2024, during which the bidding procedure was conducted in compliance with the requirements of local, state, and federal regulations; and

 

WHEREAS, Hurt Electric Inc., a qualified and competent bidder, submitted the lowest responsive and responsible bid in the amount of $317,000.00; therefore, be it,

 

RESOLVED, by the Commissioners of the Housing Authority that they hereby authorize and approve accepting the bid of and entering into a contract with Hurt Electric Inc. for Electrical for Single-Family Market-Rate Townhomes Phase 5C-1 at Westlawn Gardens Phase 2; and, be it

 

FURTHER RESOLVED, that funds for these services will come from the State of Wisconsin American Rescue Plan Act (ARPA) and Housing Authority Non-Federal sources; and, be it

 

FURTHER RESOLVED, that the proper officers of the Housing Authority be and hereby are authorized and directed to properly execute said contract for and on behalf of the Housing Authority; and, be it

 

FURTHER RESOLVED, that if any change orders including the time of performance are needed, the Chairman and Secretary-Executive Director may approve such request without any further action of the Commissioners of the Housing Authority; and, be it

 

FURTHER RESOLVED, that all of above is contingent upon receiving the approval of the U.S. Department of Housing and Urban Development, if required; and, be it

 

FURTHER RESOLVED, that all acts previously performed relative to this matter by the Commissioners and the Secretary-Executive Director of the Housing Authority be and hereby are approved, ratified, and confirmed in all respects.

 

 

Requestor

 

Drafter

Housing Management, Warren Jones, 4/4/2024