Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $2,870,000 for a total estimated cost of these projects being $3,927,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $2,870,000. The total estimated cost of these projects is $3,877,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
1st Aldermanic District
W. Hopkins St. - 250 feet m/l north of W. Fiebrantz Ave. (at N. 34th St.) (WT410051101) File Number 040112: Water main alteration. (Nonassessable Water Fund -- $40,000). The total estimated cost for this project including the requested amount is $50,000. This project is anticipated to be completed during the fall of the 2006 construction season.
Area bounded by W. Villard Ave., N. 19th St., N. 22nd St., and the alley south of W. Villard Ave. (SW170050114) File Number 051443: Sanitary sewer relocation. (Nonassessable Expansion of Capacity Sewer Fund -- $391,000). The total estimated cost for this project including the requested amount is $416,000. This project is anticipated to be completed during the 2006/2007 construction season.
2nd and 9th Aldermanic District
N. 76th St. - W. Florist Ave. to W. Clinton Ave. (WT410061130) File Number 051443: Water main alteration. (Nonassessable Water Fund -- $95,000). The total estimated cost for this project including the requested amount is $110,000. This project is anticipated to be completed during the fall of the 2006 construction season.
3rd Aldermanic District
Cherry Street Bascule Bridge (BR100060104) File Number 060370: Bridge repairs and repairs to the northwest retaining wall. The total estimated cost for this project is $50,000. This project is anticipated to be completed during the 2006/2007 construction season.
N. Murray Ave. - E. North Ave. to E. Bradford Ave. (SM495060025) File Number 060028: Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $204,000). The total estimated cost for this project including the requested amount is $216,000. This project is anticipated to be completed during the 2006/2007 construction season.
4th Aldermanic District
W. McKinley Bl. - N. 27th St. to N. 35th St. (ST211060181) File Number 060370: Install traffic calming speed humps. (Nonassessable Reconstruction Paving Fund -- $15,000). The total estimated cost for this project including the requested amount is $15,000. This project is anticipated to be completed during the 2006 construction season.
N. 18th St. - 130 feet m/l south of W. Galena St. to W. Galena St. (WT410051104) File Number 040112: Relay water main. (Nonassessable Water Fund -- $35,000). The total estimated cost for this project including the requested amount is $45,000. This project is anticipated to be completed during the fall of the 2006 construction season.
N. 22nd St. - 350 feet m/l south of W. Michigan St. to W. Michigan St. (WT410051001) File Number 050318: Relay water main. (Nonassessable Water Fund -- $50,000, additional funds.) The total estimated cost for this project including the requested amount is $160,000. This project is anticipated to be completed during the 2006 construction season.
5th Aldermanic District
W. Appleton Ave. at W. Congress St. (WT410061056) File Number 051222: Water main alteration. (Nonassessable Water Fund -- $15,000). The total estimated cost for this project including the requested amount is $30,000. This project is anticipated to be completed during the fall of the 2006 construction season.
6th Aldermanic District
E. Brown St. - N. 1st St. to N. Killian Pl. (WT410061021) File Number 041695: Relay water main. (Nonassessable Water Fund -- $170,000). The total estimated cost for this project including the requested amount is $180,000. This project is anticipated to be completed during the fall of the 2006 construction season.
11th Aldermanic District
W. Morgan Ave. - The Kinnickinnic River to S. 35th St. (SM495050048) File Number 051540: Relay sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $290,000, additional funds). The total estimated cost for this project including the requested amount is $1,025,000. This project is anticipated to be completed during the 2006 construction season.
13th Aldermanic District
S. 13th St. - W. Grange Ave. to 800 feet m/l south of W. Boden Ct. (WT410061128) File Number 051082: Relay water main. (Nonassessable Water Fund -- $1,050,000). The total estimated cost for this project including the requested amount is $1,065,000. This project is anticipated to be completed during the spring of the 2007 construction season.
15th Aldermanic District
N. 24th St. - W. North Ave. to W. Medford Ave. (WT410061063) File Number 060370: Relay water main. (Nonassessable Water Fund -- $95,000). The total estimated cost for this project including the requested amount is $110,000. This project is anticipated to be completed during the fall of the 2006 construction season.
N. 37th Pl. (Vacated) - 175 feet m/l south of W. McKinley Ave. to W. McKinley Ave. (WT410051105) File Number 040112: Abandoning water main. (Nonassessable Water Fund -- $5,000). The total estimated cost for this project including the requested amount is $15,000. This project is anticipated to be completed during the fall of the 2006 construction season.
N. 40th St. - W. Lloyd St. to W. Garfield Ave. (WT410061034) File Number 041695: Relay water main. (Nonassessable Water Fund -- $140,000). The total estimated cost for this project including the requested amount is $150,000. This project is anticipated to be completed during the fall of the 2006 construction season.
City of West Allis
S. 56th St. at W. Rogers St. (WT410061092) File Number 051658: Relay water main. (Nonassessable Water Fund -- $275,000). The total estimated cost for this project including the requested amount is $290,000. This project is anticipated to be completed during the spring of the 2007 construction season.
; now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
Requestor
Infrastructure Services Division
Drafter
mld:lk
nfr14
07/19/06