Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SIDEWALKS, SPECIAL ASSESSMENTS, STREET IMPROVEMENTS
Attachments: 1. Infr. Serv. Div. Cover Letter.doc, 2. Fiscal Note.pdf
 
Number
010898
Version
SUBSTITUTE 1
Reference
991572
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held.  The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:
 
4th Aldermanic District
 
N. 12th St. - W. Wisconsin Ave. to W. Highland Ave. (ST32000601) (2105-00-70) File Number 991572:  Concrete pavement reconstruction and asphalt pavement resurfacing, replace curb and gutter and sidewalk and driveway approaches where needed, special treatment, sodding, and grading. (Marquette Fund -- $5,400; State or Federal Funds -- $314,000; State/Federal Grantor Paving Fund -- $50,000; Assessable Reconstruction Paving Fund -- $41,000; Nonassessable Reconstruction Paving Fund -- $66,000) These funds are to be transferred to the construction account ST32000610.
 
N. 16th St. - W. Clybourn St. to W. Wisconsin Ave. (ST32000401) (2615-08-70) File Number 991572:  Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where needed, special treatment, sodding, and grading. (Marquette Fund -- $8,800; State or Federal Funds -- $136,500; State/Federal Grantor Paving Fund -- $24,100; Assessable Reconstruction Paving Fund -- $31,400; Nonassessable Reconstruction Paving Fund -- $12,400) These funds are to be transferred to the construction account ST32000410.
 
W. Wisconsin Ave.  - N. 11th St. to N. 20th St. (ST32000501) (2190-07-70) File Number 991572:  Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where needed, special treatment, sodding, and grading. (Marquette Fund -- $248,400; State or Federal Funds -- $789,000; State/Federal Grantor Paving Fund -- $151,000; Assessable Reconstruction Paving Fund -- $199,000; Nonassessable Reconstruction Paving Fund -- $58,000) These funds are to be transferred to the construction account ST32000510.
 
8th and 12th Aldermanic Districts
 
W. Mitchell St. - S. Muskego Ave. to S. Layton Blvd. (ST21110101) File Number 990755:  Concrete pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where needed, sodding, and grading. (Assessable Reconstruction Paving Fund -- $276,400; Nonassessable Reconstruction Paving Fund -- $400,100)
 
10th Aldermanic District
 
W. Keefe Ave. - N. Sherman Blvd. to N. 51st St. (ST21110108) File Number 991271:  Asphalt pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where needed, sodding, and grading. (Assessable Reconstruction Paving Fund -- $77,200; Nonassessable Reconstruction Paving Fund -- $408,100)
 
;and
 
Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and
 
Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it
 
Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works' Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it
 
Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
 
Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances, and, be it
 
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it
 
Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it
 
Further Resolved, That the City Engineer and the Commissioner of Public Works are hereby authorized to negotiate and enter into an agreement with the State of Wisconsin, Department of Transportation for the City to undertake construction management duties on the following projects: N. 12th St. (ST32000601) (2105-00-70), N. 16th St. (ST32000401) (2615-08-70), and W. Wisconsin Ave. (ST32000501) (2190-07-70); and, be it
 
Further Resolved, That the City Engineer is authorized and directed to approve and make periodic payments to the State of Wisconsin, Department of Transportation after receipt of invoices from said State for the City's share of the costs for said projects: N. 12th St. (ST32000601) (2105-00-70), N. 16th St. (ST32000401) (2615-08-70), and W. Wisconsin Ave. (ST32000501) (2190-07-70); and, be it
 
Further Resolved, That upon the completion of projects N. 12th St. (ST32000601) (2105-00-70), N. 16th St. (ST32000401) (2615-08-70), and W. Wisconsin Ave. (ST32000501) (2190-07-70) and a determination of the actual costs, it is understood that if the City of Milwaukee's share is less than the amount previously paid, the difference will be refunded to said City; and, be it
 
Further Resolved, That projects N. 12th St. (ST32000601) (2105-00-70), N. 16th St. (ST32000401) (2615-08-70), and W. Wisconsin Ave. (ST32000501) (2190-07-70) will be billed after January 1, 2004, but not before 12 months after the project contract has been completed; and, be it
 
Further Resolved, That projects W. Keefe Ave. (ST21110108) and W. Mitchell St. (ST21110101) will be billed after January 1, 2005, but not before 12 months after the project contract has been completed.
 