Title

Substitute Resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $267,000 for a total estimated cost of these projects being $1,551,000.

Analysis

This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $267,000 with the total cost estimated to be $1,551,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

 

1st Aldermanic District

 

N. Teutonia Ave. - W. Mill Rd. to W. Good Hope Rd. (SM499260002) Installing bioswales. (Nonassessable Water Quality Fund -- $20,000). The total estimated cost of this project including the requested amount is $300,000. This project is anticipated to be completed during the 2029 construction season.

 

4th Aldermanic District

 

E. Erie St. - 150’+/- northwest of N. Broadway to N. Broadway (SM495260015) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost of this project including the requested amount is $44,000.  This project is anticipated to be completed during the 2026 construction season.

 

E. Summerfest Pl. - E. Erie St. to N. Harbor Dr. (SM495260016) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $20,000). The total estimated cost of this project including the requested amount is $392,000.  This project is anticipated to be completed during the 2026 construction season.

 

6th, 7th and 15th Aldermanic Districts

 

Hopkins Street Protected Bike Lane - W. Capitol Dr. to N. Teutonia Ave. (SM499260001) Installing bioswales. (Nonassessable Water Quality Fund -- $200,000). The total estimated cost of this project including the requested amount is $600,000. This project is anticipated to be completed during the 2026/2027 construction season.

 

14th Aldermanic District

 

W. Oklahoma Ave. - 600’+/- east of S. 6th St. to S. 6th St. (SM495260017) Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost of this project including the requested amount is $215,000.  This project is anticipated to be completed during the 2026 construction season.

 

;and, be it

 

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 