File #: 100492    Version: 0
Type: Resolution Status: Passed
File created: 9/1/2010 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 9/21/2010
Effective date:    
Title: Resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $222,000 for a total estimated cost of these projects being $4,546,000.
Sponsors: THE CHAIR
Indexes: ALLEY IMPROVEMENTS, PUBLIC IMPROVEMENTS, STREET IMPROVEMENTS
Attachments: 1. Cover Letter, 2. Fiscal Note, 3. Letter, 4. Hearing Notice List

Number

100492

Version

ORIGINAL

Sponsor

THE CHAIR

Title

Resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $222,000 for a total estimated cost of these projects being $4,546,000.

Analysis

This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed.  After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable.  A resolution will be submitted after the Public Hearing authorizing construction.  The City cost for engineering these projects is estimated to be $222,000 with the total cost estimated to be $4,546,000.

Body

Resolved, By the Common Council of the City of Milwaukee that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:

 

1st Aldermanic District

 

N. 35th St. - W. Villard Ave. to W. Silver Spring Dr. (ST21100111):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $30,000, Additional Funds).  The total estimated cost for this project including the requested amount is $468,000.  This project is anticipated to be completed during the 2010 construction season.

 

Alley between W. Capitol Dr., W. Fiebrantz Ave., N. 14th St., and N. 15th St. (ST212100104):  Paving the alley with concrete.  Doing all the necessary grading pertaining to said work.  (Nonassessable Alley Paving Fund -- $5,000, Additional Funds).  The total estimated cost for this project including the requested amount is $95,000.  This project is anticipated to be completed during the 2011 construction season.

 

2nd Aldermanic District

 

W. Leon Terr. - N. 60th St. to W. Hampton Ave./W. Constance Ave. (ST211120154):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $26,000).  The total estimated cost for this project including the requested amount is $324,000.  This project is anticipated to be completed during the 2012 construction season.

 

N. 66th St. - W. Capitol Dr. to W. Congress St. (ST211090119):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $25,000, Additional Funds).  The total estimated cost for this project including the requested amount is $360,000.  This project is anticipated to be completed during the 2010 construction season.

 

9th Aldermanic District

 

W. County Line Rd. - N. 68th St. to N. 91st St. (Rural Cross Section) (ST211100132):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $12,000, Additional Funds).  The total estimated cost for this project including the requested amount is $2,312,000.  This project is anticipated to be completed during the 2011 construction season.

 

N. Michele St. - W. Beatrice St. to N. 96th St. (ST211120155):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $15,000).  The total estimated cost for this project including the requested amount is $157,000.  This project is anticipated to be completed during the 2012 construction season.

 

N. 81st St. - W. Clovernook St. to W. Acacia St. (ST21190232):  Paving the roadway with concrete.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $10,000, Additional Funds).  The total estimated cost for this project including the requested amount is $113,000.  This project is anticipated to be completed during the 2010 construction season.

 

N. 82nd Ct. - A point south of W. Clovernook St. to W. Clovernook St. (ST211020107):  Paving the roadway with concrete.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $10,000, Additional Funds).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2010 construction season.

 

10th Aldermanic

 

W. Main St. - S. 70th St. to S. 76th St. (ST211080108):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $31,000, Additional Funds).  The total estimated cost for this project including the requested amount is $363,000.  This project is anticipated to be completed during the 2011 construction season.

 

14th Aldermanic District

 

S. Pennsylvania Ave. - E. Eden Pl. to E. Morgan Ave. (ST211120156):  Paving the roadway with concrete.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $8,000).  The total estimated cost for this project including the requested amount is $54,000.  This project is anticipated to be completed during the 2012 construction season.

 

Various Aldermanic Districts

 

Administration cost for 2011 Sidewalk Paving Engineering (ST230110138):  (Nonassessable 2010 Budgeted Funds -- $50,000).  The total estimated cost for this project including the requested amount is $200,000.  This project is anticipated to be completed during the 2011 construction season; and, be it

 

Further Resolved, That the abutting and adjacent properties be assessed a portion of the cost, said assessment to be recommended by the Commissioner of Public Works in his report; and, be it

 

Further Resolved, That all assessments and payments be made in accordance with Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That all City departments are authorized to do engineering, surveying, preparing of plans, and estimates of cost thereof, to be utilized in the preparation of said report of the Commissioner of Public Works; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

MLD:dr

Apr 1

08/25/10