Number
070267
Version
SUBSTITUTE 2
Reference
061095
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $4,886,000 for a total estimated cost of these projects being $5,221,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $4,886,000. The total estimated cost of these projects is $5,221,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
1st Aldermanic District
W. Custer Ave. (Extended) - N. Teutonia Ave. to 150 feet m/l west of N. Teutonia Ave. (SM495060082) File Number 061095: Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $23,000). The total estimated cost for this project including the requested amount is $28,000. This project is anticipated to be completed during the 2007 construction season.
W. Good Hope Rd. - A point 270 feet m/l east of N. Teutonia Ave. to N. Teutonia Ave. (WT410071075) File Number 051658: Relay water main. (Nonassessable Water Fund -- $55,000). The total estimated cost for this project including the requested amount is $70,000. This project is anticipated to be completed during the 2007 construction season.
2nd Aldermanic District
W. Lancaster Ave. - N. 69th St. to W. Leon Tr. (WT410061127) File Number 050806: Relay water main. (Nonassessable Water Fund -- $175,000). The total estimated cost for this project including the requested amount is $190,000. This project is anticipated to be completed during the 2007 construction season.
W. Leon Tr. - N. 69th St. to N. 72nd St. (WT410061012) File Number 041695: Relay water main. (Nonassessable Water Fund -- $290,000). The total estimated cost for this project including the requested amount is $300,000. This project is anticipated to be completed during the 2007 construction season.
N. 69th St. - W. Leon Tr. to W. Villard Ave. (WT410061010) File Number 041695: Relay water main. (Nonassessable Water Fund -- $370,000). The total estimated cost for this project including the requested amount is $380,000. This project is anticipated to be completed during the 2007 construction season.
N. 70th St. - W. Leon Tr. to W. Villard Ave. (WT410061011) File Number 041695: Relay water main. (Nonassessable Water Fund -- $290,000). The total estimated cost for this project including the requested amount is $300,000. This project is anticipated to be completed during the 2007 construction season.
4th Aldermanic District
W. Michigan St. - N. 24th St. to N. 27th St. (SM495060063) File Number 060843: Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $246,000). The total estimated cost for this project including the requested amount is $261,000. This project is anticipated to be completed during the 2007 construction season.
5th Aldermanic District
W. Lisbon Ave. - N. 82nd St. to N. 83rd St. (SM495060052) File Number 060574: Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $33,000). The total estimated cost for this project including the requested amount is $40,000. This project is anticipated to be completed during the 2007 construction season.
6th Aldermanic District
N. 19th St. - W. Vienna Av. to W. Atkinson Ave. (SM495060076) File Number 061095: Relay sanitary and storm sewers. (Nonassessable Sewer Maintenance Relay Fund -- $326,000). The total estimated cost for this project including the requested amount is $338,000. This project is anticipated to be completed during the 2007 construction season.
8th Aldermanic District
W. Greenfield Ave. - S. 26th St. to S. Layton Blvd. (SM495070100) File Number 070266: Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $61,000). The total estimated cost for this project including the requested amount is $61,000. This project is anticipated to be completed during the 2007 construction season.
W. Mitchell St. - S. 33rd St. to S. 37th St. (SM495060007) File Number 051658: Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $270,000). The total estimated cost for this project including the requested amount is $291,000. This project is anticipated to be completed during the 2007 construction season.
10th Aldermanic District
W. Adler St. - S. 70th St. to S. 72nd St. (SM495060081) File Number 061380: Sanitary relay and sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $59,000). The total estimated cost for this project including the requested amount is $69,000. This project is anticipated to be completed during the 2007 construction season.
S. Dana Ct. - W. Fairview Ave. to 400 feet m/l north of W. Fairview Ave. (SM495060080) File Number 061095: Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $41,000). The total estimated cost for this project including the requested amount is $46,000. This project is anticipated to be completed during the 2007 construction season.
W. Park Hill Ave. - N. 60th St. to N. 62nd St. (SM495060013) File Number 061288: Relay sanitary and storm sewers. (Nonassessable Sewer Maintenance Relay Fund -- $184,000). The total estimated cost for this project including the requested amount is $209,000. This project is anticipated to be completed during the 2007 construction season.
W. Stevenson St. - N. 60th St. to N. 63rd St. (SM495060065) File Number 060843: Relay sanitary and storm sewers. (Nonassessable Sewer Maintenance Relay Fund -- $378,000). The total estimated cost for this project including the requested amount is $393,000. This project is anticipated to be completed during the 2007 construction season.
N. Story Parkway - N. Pinecrest St. to W. Blue Mound Rd. (SM495060053) File Number 060574: Relay sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $403,000). The total estimated cost for this project including the requested amount is $438,000. This project is anticipated to be completed during the 2007 construction season.
W. Washington Bl. (North Side) - N. 47th St. to N. 50th St. (WT410070001) File Number 051658: Relay water main. (Nonassessable Water Fund -- $215,000). The total estimated cost for this project including the requested amount is $230,000. This project is anticipated to be completed during the 2007 construction season.
W. Washington Bl. (South Side) - N. 49th St. to N. 50th St. (WT410070002) File Number 051658: Abandoning water main. (Nonassessable Water Fund -- $15,000). The total estimated cost for this project including the requested amount is $30,000. This project is anticipated to be completed during the 2007 construction season.
N. 59th St. - N. Hawley Rd. to a point 175 feet m/l north of N. Hawley Rd. (SM495060077) File Number 061095: Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $25,000). The total estimated cost for this project including the requested amount is $30,000. This project is anticipated to be completed during the 2007 construction season.
N. 62nd St. - W. Stevenson St. to W. St. Paul Ave. (SM495060064) File Number 060843: Relay sanitary and storm sewers. (Nonassessable Sewer Maintenance Relay Fund -- $498,000). The total estimated cost for this project including the requested amount is $518,000. This project is anticipated to be completed during the 2007 construction season.
15th Aldermanic District
W. Clarke St. - N. 36th St. to N. 37th St. (SM495060066) File Number 060843: Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $123,000). The total estimated cost for this project including the requested amount is $135,000. This project is anticipated to be completed during the 2007 construction season.
W. Garfield Ave. - N. 24th St. to N. 25th St. (WT410071064) File Number 051658: Relay water main. (Nonassessable Water Fund -- $75,000). The total estimated cost for this project including the requested amount is $90,000. This project is anticipated to be completed during the 2007 construction season.
W. Garfield Ave. - N. 20th St. to N. 24th St. (SM495070095) File Number070266: Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $306,000). The total estimated cost for this project including the requested amount is $306,000. This project is anticipated to be completed during the 2007 construction season.
W. Juneau Ave. - N. 35th St. to N. 38th St. (WT410071026) File Number 051658: Relay water main. (Nonassessable Water Fund -- $145,000). The total estimated cost for this project including the requested amount is $160,000. This project is anticipated to be completed during the 2007 construction season.
N. 37th St. - W. Wright St. to W. Clarke St. (SM495060008) File Number 051658: Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $170,000). The total estimated cost for this project including the requested amount is $183,000. This project is anticipated to be completed during the 2007 construction season.
N. 39th St. - W. Cherry St. to W. Galena St. (WT410071027) File Number 051658: Relay water main. (Nonassessable Water Fund -- $110,000). The total estimated cost for this project including the requested amount is $125,000. This project is anticipated to be completed during the 2007 construction season.
; now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
Requestor
Infrastructure Services Division
Drafter
mld:lk
nfr12