File #: 140040    Version:
Type: Resolution Status: Passed
File created: 4/22/2014 In control: COMMON COUNCIL
On agenda: Final action: 5/13/2014
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $8,370,000 for a total estimated cost of these projects being $9,329,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Hearing Notice List
Number
140040
Version
Substitute 1
Reference
131376
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $8,370,000 for a total estimated cost of these projects being $9,329,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $8,370,000.  The total estimated cost of these projects is $9,329,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
 
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
 
1st Aldermanic District
 
N. 23rd St. - 310 feet m/l south of W. Hope Ave. to W. Hope Ave. (SM495140005) File Number 131376:  Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $78,000).  The total estimated cost for this project including the requested amount is $90,000.  This project is anticipated to be completed during the 2014 construction season.
 
3rd Aldermanic District
 
N. Bremen St. - E. Hadley St. to E. Locust St. (SM495140018) File Number 131475:  Installing new storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $250,000).  The total estimated cost for this project including the requested amount is $265,000.  This project is anticipated to be completed during the 2014 construction season.
 
6th Aldermanic District
 
N. Holton St. - E. Nash St. to 30 feet m/l north of E. Nash St. (SM495140039) File Number 140039:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $33,000).  The total estimated cost for this project including the requested amount is $45,000.  This project is anticipated to be completed during the 2014 construction season.
 
7th Aldermanic District
 
N. 44th St. - W. Center St. to W. Locust St. (SM495120108) File Number 130868:  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $553,000).  The total estimated cost for this project including the requested amount is $565,000.  This project is anticipated to be completed during the 2014 construction season.
 
N. 46th St. - W. Auer Ave. to W. Concordia Ave. (SM495120065) File Number 120702:  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $270,000).  The total estimated cost for this project including the requested amount is $285,000.  This project is anticipated to be completed during the 2014 construction season.
 
8th Aldermanic District
 
S. 21st St. - W. Greenfield Ave. to W. Mitchell St. (SM495130093) File Number 131076:  Combined large diameter sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $555,000).  The total estimated cost for this project including the requested amount is $570,000.  This project is anticipated to be completed during the 2014 construction season.
 
S. 28th St. - W. Forest Home Ave. to W. Hayes Ave. (SM495120014) File Number 120702:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $105,000).  The total estimated cost for this project including the requested amount is $120,000.  This project is anticipated to be completed during the 2014 construction season.
 
S. 35th St. - 300 feet south of W. Burnham St. to 270 feet north of W. Mitchell St. (SM495140024) File Number 131475:  Relaying combined sewer and storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $335,000).  The total estimated cost for this project including the requested amount is $350,000.  This project is anticipated to be completed during the 2014 construction season.
 
8th and 11th Aldermanic Districts
 
S. 35th St. Bridge (2700S) over the Union Pacific Railroad (BR100140109) File Number 140039:  Repair of bridge deck and superstructure caused by train impact.  (City Share Non-assessable Structure Fund -- $1,250,000).  The total estimated cost for this project including the requested amount is $1,265,000.  This project is anticipated to be completed during the 2014 construction season.
 
8th and 12th Aldermanic Districts
 
W. Mitchell St. - S. 20th St. to S. 21st St. (SM495140030) File Number 131587:  Combined large diameter sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $160,000).  The total estimated cost for this project including the requested amount is $175,000.  This project is anticipated to be completed during the 2014 construction season.
 
10th Aldermanic District
 
W. Lisbon Ave. - N. 60th St. to W. Avondale Blvd. (SM495130002) File Number 121332:  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $335,000).  The total estimated cost for this project including the requested amount is $350,000.  This project is anticipated to be completed during the 2014 construction season.
 
N. 55th St. - W. Burleigh St. to W. Auer Ave./W. Louise Pl. (SM495120069) File Number 120702:  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $138,000).  The total estimated cost for this project including the requested amount is $150,000.  This project is anticipated to be completed during the 2014 construction season.
 
N. 59th St. - W. Center St. to W. Appleton Ave. (US 41) (SM495130007) File Number 121332:  Relaying sanitary sewer and storm sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $108,000).  The total estimated cost for this project including the requested amount is $120,000.  This project is anticipated to be completed during the 2014 construction season.
 
N. 68th St. - W. Center St. to W. Lisbon Ave. (SM495120090) File Number 130868:  Relaying sanitary and storm sewers.  (Nonassessable Sewer Maintenance Relay Fund -- $513,000).  The total estimated cost for this project including the requested amount is $525,000.  This project is anticipated to be completed during the 2014 construction season.
 
11th Aldermanic District
 
W. Euclid Ave. - S. 42nd St. to S. 43rd St. (SM495100029) File Number 091131):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $63,000).  The total estimated cost for this project including the requested amount is $75,000.  This project is anticipated to be completed during the 2014 construction season.
 
S. 42nd St. - W. Forest Home Ave. to 100 feet m/l south of W. Euclid Ave. (SM495100028) File Number 091131:  Relaying sanitary and storm sewers.  (Nonassessable Sewer Maintenance Relay Fund -- $322,000).  The total estimated cost for this project including the requested amount is $334,000.  This project is anticipated to be completed during the 2014 construction season.
 
12th Aldermanic District
 
W. Arrow St. - S. Union St. to S. Comstock Ave. (SM495100074) File Number 100013:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $83,000).  The total estimated cost for this project including the requested amount is $95,000.  This project is anticipated to be completed during the 2014 construction season.
 
W. Scott St. - S. 10th St. to S. 15th St. (SM495130068) File Number 130599:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $778,000).  The total estimated cost for this project including the requested amount is $790,000.  This project is anticipated to be completed during the 2014 construction season.
 
S. 3rd St. - W. Lapham Blvd. to W. Orchard St. (SM495130063) File Number 130599:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $168,000).  The total estimated cost for this project including the requested amount is $180,000.  This project is anticipated to be completed during the 2014 construction season.
 
S. 17th St. - 150 feet m/l south of W. Becher St. to W. Grant St. (SM495130086) File Number 130868:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $115,000).  The total estimated cost for this project including the requested amount is $130,000.  This project is anticipated to be completed during the 2014 construction season.
 
12th and 14th Aldermanic Districts
 
S. 11th St. - 400 feet m/l south of W. Cleveland Ave. to 100 feet m/l south of W. Harrison Ave. (SM495120054) File Number 120371:  Relaying combined sewer and installing new storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $378,000.  The total estimated cost for this project including the requested amount is $390,000.  This project is anticipated to be completed during the 2014 construction season.
 
14th Aldermanic District
 
S. Howell Ave. Bridge over the Union Pacific Railroad (BR100140108) File Number 140039:  Repair of bridge deck and superstructure caused by train impact.  (City Share Non-assessable Structure Fund -- $800,000).  The total estimated cost for this project including the requested amount is $815,000.  This project is anticipated to be completed during the 2014 construction season.
 
 
City Wide
 
2014 Large and Medium Diameter Sewer Exams (SM495140047) File Number 140039:  (Nonassessable Sewer Maintenance Relay Fund -- $480,000).  The total estimated cost for this project including the requested amount is $500,000.  This project is anticipated to be completed during the 2014 construction season.
 
Various Aldermanic Districts
 
High impact streets resurface by contract, #3 (ST216140103) File Number 131476:  Asphalt pavement overlay.  (Nonassessable Reconstruction Paving Fund -- $300,000, Additional Funds)  The total estimated cost for this project including the requested amount is $935,000.  This project is anticipated to be completed during the 2014 construction season.
 
High impact streets resurface by contract, #5 (ST216140105) File Number 131475:  Asphalt pavement overlay.  (Nonassessable High Impact Streets -- $200,000).  The total estimated cost for this project including the requested amount is $210,000.  This project is anticipated to be completed during the 2014 construction season.
 
now, therefore, be it
 
Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it
 
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
 
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
 
Requestor
Infrastructure Services Division
Drafter
MLD:dr
Nfr 11
04/25/2014