Skip to main content
powered help
header-left header-center header-right
File #: 250335    Version: 0
Type: Resolution Status: In Council-Adoption
File created: 6/24/2025 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action:
Effective date:    
Title: Resolution directing the Commissioner of Public Works to execute State/Municipal Agreements for a State-Let Highway Project with the Wisconsin Department of Transportation for the construction of IH-43 North South Freeway from Halyard Street to Capitol Drive, and to set up funds for construction at an estimated total cost of $22,020,000 with an estimated City share of $2,000 and a grantor share of $22,018,000.
Sponsors: THE CHAIR
Attachments: 1. 1228-22-73 SMA Financial IH43 Halyard-Capitol-Milw Water.pdf, 2. 1228-22-73 SMA Maintenance IH43 Halyard-Capitol-Milw Water.pdf, 3. Resolution Certification - 1228-22-73 - Comptroller Office - Milw Water - Signed.pdf

Number

 250335

Version

ORIGINAL

Reference

Sponsor

THE CHAIR

Title

Resolution directing the Commissioner of Public Works to execute State/Municipal Agreements for a State-Let Highway Project with the Wisconsin Department of Transportation for the construction of IH-43 North South Freeway from Halyard Street to Capitol Drive, and to set up funds for construction at an estimated total cost of $22,020,000 with an estimated City share of $2,000 and a grantor share of $22,018,000.

Analysis

This resolution directs the Commissioner of Public Works to execute State/Municipal Agreements with the Wisconsin Department of Transportation for the construction of IH-43 North South Freeway from Halyard Street to Capitol Drive. The State/Municipal Agreements provide for 90 percent Federal and State aid and 10 percent local cost sharing. The total estimated cost of this project is $24,020,000 with an estimated City share of $2,000 and a grantor share of $24,018,000.

 

Body

Whereas, State/Municipal Agreements have been requested and received from the Wisconsin Department of Transportation (WisDOT) to be executed by the City of Milwaukee for the construction of IH-43 North South Freeway from Halyard Street to Capitol Drive, with Federal and State aid under the State Highway Rehabilitation Program; and

 

Whereas, The Department of Public Works shall notify the Common Council of the City of Milwaukee of project cost overruns and changes in scope approved by the Department of Public Works; and

 

Whereas, The Common Council of the City of Milwaukee recognizes that the City may be 100 percent liable for project cost overruns and changes in scope as approved by the Department of Public Works; and

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is hereby authorized to execute the agreements for the programming, design, construction, and maintenance of the aforementioned connecting highway project with Federal and/or State aid, copies of which are attached as part of this file, and are incorporated into this resolution by reference as though set forth in full; and, be it

 

Further Resolved, That the City Comptroller is hereby authorized to create within the Capital Improvement Fund, Grant and Aid Projects, the necessary Project Grant Chartfield Values for construction for the project (Expenditure) and transfer to any of these accounts the amount required under the grant agreement and City Accounting Policy but not to exceed a 10 percent increase of the total amounts reserved for the grantor’s share and local share or $5,000, whichever is greater, as follows:

 

State I.D. 1228-22-73

IH-43 North South Freeway

Halyard Street to Capitol Drive

 

City Share

WK64409002

Fund 0410

$2,000

 

Grantor Non-Reimbursable Funds

$22,018,000

 

Estimated Total Construction $22,020,000

Total Engineering Previously Authorized $0

 

Current Estimated Cost of Total Project Including this Resolution $24,020,000

Original Estimate Cost of Total Project $24,020,000

 

Further Resolved, That the City Engineer is hereby authorized to approve and make periodic payments to the WisDOT upon receipt of invoices for the City’s share of the project costs.

 

Requestor

Department of Public Works

Milwaukee Water Works

 

Drafter

Water Engineering Section

Joshua Iwen

June 5, 2025