Number
250514
Version
ORIGINAL
Sponsor
THE CHAIR
Title
Resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $282,000 for a total estimated cost of these projects being $3,744,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $282,000 with the total cost estimated to be $3,744,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:
1st Aldermanic District
N. 13th St. - 330' south of W. Lawn Ave. to W. Custer Ave. (WT410230677) File Number 211861: Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $0. Nonassessable Water Budget Line 6410 -- $15,000 additional funding.) The total estimated cost of the project including the requested amount is $170,000. This project is anticipated to be completed during the 2026 construction season.
4th Aldermanic District
N. Water St. - 110' south of E. Erie St. to E. Clybourn St. (WT410260642) Relaying water main and lead replacement of service. (Nonassessable Water Fund Budget Line 5010 -- $1,000. Nonassessable Water Budget Line 6410 -- $69,000.) The total estimated cost of the project including the requested amount is $1,120,000. This project is anticipated to be completed during the 2026 construction season.
N. Water St. - E. Erie St to E. Clybourn St. (SM499250017) Installing bioswales. (Nonassessable Water Quality Fund -- $30,000). The total estimated cost of this project including the requested amount is $200,000. This project is anticipated to be completed during the 2026-2027 construction season.
N. Water St. - E. Kilbourn St. to E. Pleasant St. (SM499250016) Installing bioswales. (Nonassessable Water Quality Fund -- $30,000). The total estimated cost of this project including the requested amount is $200,000. This project’s anticipated completion date is to be determined.
10th Aldermanic District
High impact paving: N. Hawley Rd., W. Wisconsin Ave.; 2026 Group 1 (ST216250115) Asphalt surface overlay. (Nonassessable High Impact Paving Fund -- $15,000). The total estimated cost of this project including the requested amount is $450,000. This project is anticipated to be completed during the 2026-2027 construction season.
13th Aldermanic District
S. 20th St. - W. Grange Ave. to W. Klein Ave. (WT410220714) File Number 201669: Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $0. Nonassessable Water Budget Line 6410 -- $20,000 additional funding) The total estimated cost of the project including the requested amount is $275,000. This project is anticipated to be completed during the 2026 construction season.
S. Adams Ave. - E. Bolivar Ave. to E. Armour Ave. (SM495250039) Relaying sanitary sewer. (Nonassessable Sanitary Relay Fund -- $20,000) The total estimated cost of the project including the requested amount is $476,000. This project is anticipated to be completed during the 2026 construction season.
S. Burrell St. - E. Van Norman Ave. to E. Armour Ave. (SM495250038) Relaying sanitary sewer. (Nonassessable Sanitary Relay Fund -- $12,000) The total estimated cost of the project including the requested amount is $87,000. This project is anticipated to be completed during the 2026 construction season.
S. Quincy Ave. - 1050’ north of E. Armour Ave. to E. Armour Ave. (SM495250040) Relaying sanitary sewer. (Nonassessable Sanitary Relay Fund -- $20,000) The total estimated cost of the project including the requested amount is $306,000. This project is anticipated to be completed during the 2026 construction season.
15th Aldermanic District
N. 37th St. - W. Galena St. to W. Walnut St. (WT410250661) Relaying water main and lead replacement of service. (Nonassessable Water Fund Budget Line 5010 -- $1,000. Nonassessable Water Budget Line 6410 -- $19,000.) The total estimated cost of the project including the requested amount is $115,000. This project is anticipated to be completed during the 2026 construction season.
W. Walnut St. - N. 37th St. to N. 40th St. (WT410250662) Relaying water main and lead replacement of service. (Nonassessable Water Fund Budget Line 5010 -- $1,000. Nonassessable Water Budget Line 6410 -- $29,000.) The total estimated cost of the project including the requested amount is $345,000. This project is anticipated to be completed during the 2026 construction season.
;and, be it
Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
Requestor
Infrastructure Services Division
Drafter
Holly Rutenbeck
NPR 15
7/9/2025