Number
111474
Version
ORIGINAL
Sponsor
THE CHAIR
Title
Resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $576,000 for a total estimated cost of these projects being $9,772,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $576,000 with the total cost estimated to be $9,772,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:
1st and 6th Aldermanic Districts
W. Capitol Dr. - N. 13th St. to N. 15th St. (SM495120025): Sanitary and storm relay. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $311,000. This project is anticipated to be completed during the 2012 construction season.
2nd and 7th Aldermanic Districts
N. 56th St. - W. Keefe Ave. to W. Melvina St. (SM495120023): Sanitary and storm sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $219,000. This project is anticipated to be completed during the 2012 construction season.
3rd Aldermanic District
N. Astor St. - E. Hamilton St. to 170 feet m/l north of E. Land Pl. (SM495110085): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost for this project including the requested amount is $89,000. This project is anticipated to be completed during the 2012 construction season.
N. Cambridge Ave. - E. Locust St. to 455 feet m/l north of E. Locust St.; and E. Locust St. - 230 feet m/l east of N. Cambridge Ave. to N. Cambridge Ave. (SM495110064): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $205,000. This project is anticipated to be completed during the 2012 construction season.
N. Farwell Ave. - E. Brady St. to E. Royall Pl. (SM495120308): Relay combined sewer and sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $597,000. This project is anticipated to be completed during the 2012 construction season.
N. Farwell Ave. - E. Ogden Ave. to E. Brady St. (SM495120310): Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $873,000. This project is anticipated to be completed during the 2012 construction season.
Alley between E. Brady St., N. Prospect Ave., E. Royall Pl., and N. Farwell Ave. (SM495110067): New storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost for this project including the requested amount is $53,000. This project is anticipated to be completed during the 2012 construction season.
3rd and 4th Aldermanic Districts
N. Prospect Ave. - E. Albion St. to E. Royall Pl. (SM495120309): Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $196,000. This project is anticipated to be completed during the 2012 construction season.
N. Prospect Ave. - E. Ogden Ave. to E. Curtis Pl. (SM495120307): Combined sewer lining and relay storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $409,000. This project is anticipated to be completed during the 2012 construction season.
4th Aldermanic District
N. Edison St. - E. State St. to E. Highland Ave. (SM495110086): Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $1,000). The total estimated cost for this project including the requested amount is $50,000. This project is anticipated to be completed during the 2012 construction season.
N. 4th St. - W. Clybourn St. to W. Wisconsin Ave. (SM495120303): Combined and sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $479,000. This project is anticipated to be completed during the 2012 construction season.
N. 4th St. - W. Wisconsin Ave. to W. Kilbourn Ave. (SM495120304): Combined and sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $304,000. This project is anticipated to be completed during the 2012 construction season.
N. 4th St. - W. Kilbourn Ave. to W. Highland Ave. (SM495120305): Combined and sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $381,000. This project is anticipated to be completed during the 2012 construction season.
N. 4th St. - W. Highland Ave. to W. Juneau Ave. (SM495120306): Combined and sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $382,000. This project is anticipated to be completed during the 2012 construction season.
N. 24th St. - W. State St. to W. Highland Ave. (SM495120027): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $56,000. This project is anticipated to be completed during the 2012 construction season.
4th and 6th Aldermanic Districts
W. Juneau Ave. - N. Old World Third St. to N. 5th St. (SM495120302): Relay combined sewer and sanitary lateral lining. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $577,000. This project is anticipated to be completed during the 2012 construction season.
5th Aldermanic District
N. 82nd St. - W. Locust St. to W. Chambers St. (SM495110054): Storm sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost for this project including the requested amount is $58,000. This project is anticipated to be completed during the 2012 construction season.
6th Aldermanic District
E. Glover Ave. - N. Booth St. to 200 feet m/l east of N. Booth St. (SM495120022): New storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost for this project including the requested amount is $48,000. This project is anticipated to be completed during the 2012 construction season.
N. Teutonia Ave. - W. Hadley St. to W. Locust St. (SM495110065): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $127,000. This project is anticipated to be completed during the 2012 construction season.
N. 10th St. - W. Nash St. to W. Abert Pl. (SM495120031): Sanitary lining. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $65,000. This project is anticipated to be completed during the 2012 construction season.
N. 12th St. - W. Abert Pl. to W. Capitol Dr. (SM495120032): Relay sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $209,000. This project is anticipated to be completed during the 2012 construction season.
N. 13th St. - W. Burleigh St. to W. Ring St. (SM495100241): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000, Additional Funds). The total estimated cost for this project including the requested amount is $292,000. This project is anticipated to be completed during the 2012 construction season.
N. 22nd St. - W. Hopkins St. to W. Keefe Ave. (SM495120021): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $336,000. This project is anticipated to be completed during the 2012 construction season.
N. 23rd St. - W. Auer Ave. to W. Hopkins St. (SM495110068): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $103,000. This project is anticipated to be completed during the 2012 construction season.
6th and 15th Aldermanic Districts
W. Hadley St. - N. 16th St. to N. 19th St. (SM495120019): Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $311,000. This project is anticipated to be completed during the 2012 construction season.
7th Aldermanic District
N. Sherman Blvd. (east side) - W. Hadley St. to W. Locust St. (SM495110084): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $164,000. This project is anticipated to be completed during the 2012 construction season.
N. 40th St. - W. Courtland Ave. to W. Hampton Ave. (SM495110057): Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $150,000. This project is anticipated to be completed during the 2012 construction season.
N. 40th St. - W. Vienna Ave. to W. Roosevelt Dr. (SM495110074): Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $106,000. This project is anticipated to be completed during the 2012 construction season.
8th Aldermanic District
W. Mineral St. - S. 26th St. to S. Layton Ave. (SM495110073): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost for this project including the requested amount is $65,000. This project is anticipated to be completed during the 2012 construction season.
S. 30th St. - W. National Ave. to W. Pierce St. (SM495110078): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $147,000. This project is anticipated to be completed during the 2012 construction season.
S. 35th St. - 400 feet m/l south of W. Greenfield Ave. to W. Greenfield Ave. (SM495120020): Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $10,000). The total estimated cost for this project including the requested amount is $41,000. This project is anticipated to be completed during the 2012 construction season.
9th Aldermanic District
N. 107th St. - W. Brown Deer Rd. to W. County Line Rd. (WT410120004): Water main relay and alteration. (Nonassessable Water Fund Budget Line 5010 -- $10,000; Nonassessable Water Fund Budget Line 6410 -- $25,000). The total estimated cost for this project including the requested amount is $400,000. This project is anticipated to be completed during the 2013 construction season.
10th Aldermanic District
N. 59th St. - W. Vliet St. to W. McKinley Ave. (SM495120029): Sanitary lining and storm relay. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $112,000. This project is anticipated to be completed during the 2012 construction season.
N. 60th St. - W. McKinley Ave. to W. Vliet St. (SM495120028): Sanitary and storm sewer relay. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $540,000. This project is anticipated to be completed during the 2012 construction season.
12th Aldermanic District
E. Greenfield Ave. - S. Barclay St. to S. 1st St. (SM495110063): Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost for this project including the requested amount is $41,000. This project is anticipated to be completed during the 2012 construction season.
13th Aldermanic District
W. Oklahoma Ave. - S. 26th St. to S. 27th St. (SM495120024): Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $130,000. This project is anticipated to be completed during the 2012 construction season.
14th Aldermanic District
E. Dakota St. - S. Clement Ave. to S. Herman St. (SM495120030): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $65,000. This project is anticipated to be completed during the 2012 construction season.
S. Lenox St. - E. Otjen St. to E. Homer St. (SM495110075): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost for this project including the requested amount is $87,000. This project is anticipated to be completed during the 2012 construction season.
S. 5th St. - W. Becher St. to W. Lincoln Ave. (SM495110072): Combined large diameter sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $227,000. This project is anticipated to be completed during the 2012 construction season.
15th Aldermanic District
Area bounded by W. Walnut St., W. Galena St., N. 15th St., and N. 17th St. (#13) (SM495110108): New storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $1,000). The total estimated cost for this project including the requested amount is $619,000. This project is anticipated to be completed during the 2012 construction season.
N. 19th St. - W. Center St. to W. Clarke St. (SM495120026): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $148,000. This project is anticipated to be completed during the 2012 construction season.
;and, be it
Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
Requestor
Infrastructure Services Division
Drafter
MLD:dr
Npr 9
02/22/2012