powered help
header-left header-center header-right
File #: 161285    Version: 0
Type: Resolution Status: Passed
File created: 1/18/2017 In control: COMMON COUNCIL
On agenda: Final action: 2/7/2017
Effective date:    
Title: Resolution relative to the cost participation and installation of traffic control devices in conjunction with the Federal State Aid paving of South 60th Street from West Cold Spring Road to West Morgan Avenue in the 11th Aldermanic District at a total estimated cost of $243,752.01, with an estimated grantor share of $140,000, an estimated City of Milwaukee share of $85,220.70, and an estimated City of Greenfield share of $18,531.31.
Sponsors: THE CHAIR
Indexes: TRAFFIC CONTROL SIGNALS
Attachments: 1. Comptroller Certification.PDF, 2. Agreement, 3. Project Unit Cost Analysis

Number

161285

Version

ORIGINAL

Reference

140427

Sponsor

THE CHAIR

Title

Resolution relative to the cost participation and installation of traffic control devices in conjunction with the Federal State Aid paving of South 60th Street from West Cold Spring Road to West Morgan Avenue in the 11th Aldermanic District at a total estimated cost of $243,752.01, with an estimated grantor share of $140,000, an estimated City of Milwaukee share of $85,220.70, and an estimated City of Greenfield share of $18,531.31.

Analysis

This resolution authorizes the Commissioner of Public Works and Comptroller to enter into a funding agreement with the Wisconsin Department of Transportation for installation of traffic control improvements in conjunction with the Federal State Aid paving of South 60th Street from West Cold Spring Road to West Morgan Avenue in the 11th Aldermanic District at a total estimated cost of $243,752.01 with an estimated grantor share of $140,000, an estimated City of Milwaukee share of $85,220.70, and an estimated City of Greenfield share of $18,531.31, and to install these improvements upon execution of the agreement.  This resolution also authorizes the Comptroller to establish and transfer funds to the appropriate accounts for the project.  The total estimated cost of the entire project is $5,648,202.01, with a grantor share of $4,335,560, a City of Milwaukee share of $1,294,110.70, and a City of Greenfield share of $18,531.31.

Body

Whereas, The Project Agreement for the paving of South 60th Street from West Cold Spring Road to West Morgan Avenue was approved by the Common Council under File Number 140427; and,

 

Whereas, The Surface Transportation Program provides cost participation for traffic control improvements in conjunction with the paving of highways located on the Federal State Aid Highway System; and

 

Whereas, The total estimated cost of this project is $211,958.27 for the alteration and upgrade of traffic control signals and the upgrade of traffic control signs; and

 

Whereas, The total estimated cost for state review for the project is $31,793.74; and

 

Whereas, $85,220.70 is not reimbursable and is included in the Division’s 2017 Capital Purpose Project Grant Number ST320170000; and

 

Whereas, Three-quarters of the estimated local share of improvements to the traffic signal at West Cold Spring Road and South 60th Street, or $18,531.31, is billable to the City of Greenfield per a 1968 agreement; and

 

Whereas, $114,565.01 is reimbursable from the Wisconsin Department of Transportation, and should be earmarked for this project in the 2017 Capital Grant and Aids Projects Fund Project Grant Number SP032170100; and

 

Whereas, $25,434.99, is non-reimbursable from the Wisconsin Department of Transportation; and

 

Whereas,  The State cannot proceed with any project cost overruns and changes in scope of more than 5% without prior Department of Public Works approval; and   

 

Whereas, The Department of Public Works shall notify the Common Council of the City of Milwaukee at the next scheduled meeting of any such project cost overruns and changes in scope approved by the Department of Public Works; and

 

Whereas, The Common Council of the City of Milwaukee recognizes that the City may be 100% liable for any such project cost overruns and changes in scope as approved by the Department of Public Works; and

 

Whereas, The Common Council of the City of Milwaukee recognizes that the City may be liable for any costs incurred by the State should the City decide to withdraw from the project; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works and the Comptroller are authorized to enter into a funding agreement and are directed to execute the agreement with the Wisconsin Department of Transportation for the installation of traffic control facilities in conjunction with the improvements to South 60th Street from West Cold Spring Road to West Morgan Avenue with unit prices based on a predetermined estimate prepared under the Federal State aided highway program, a copy of which is attached to this resolution, and is incorporated into this resolution as though set forth in full; and be it

 

Further Resolved, That upon approval of this contract, that the Commissioner of Public Works is directed to install and modify traffic control facilities in conjunction with the improvements to South 60th Street from West Cold Spring Road to West Morgan Avenue; and, be it

 

Further Resolved, That upon completion of the project, the City of Greenfield will be billed three-quarters of the local share of the actual cost of traffic signal improvements at West Cold Spring Road and South 60th Street; and, be it

 

Further Resolved, That upon approval of this contract, the City Comptroller is hereby authorized to create within the Capital Grant and Aid Projects Fund the appropriate Project Grant Chartfield Value for this project; and transfer to these accounts the amount required under the agreement and City accounting policy, but not to exceed a ten percent increase of the total amounts reserved for the grantor’s share and local share or $5,000, whichever is greater as follows:

 

Location:

Project I.D.-2415-00-90

South 60th Street - West Cold Spring Road to West Morgan Avenue

 

City of Milwaukee Share

Fund Number-0333

Project Grant Number-ST320170000

$85,220.70

 

Grantor Reimbursable Cash - Traffic Control

Fund Number-0306

Project Grant Number-SP032170100

$114,565.01

 

City of Greenfield Share

Fund Number-0306

Project Grant Number-SP032170100

$18,531.31

 

Grantor Non-reimbursable

$25,434.99

 

Total-$243,752.01

 

Previously Authorized for Traffic Control Improvements-$0

Current Estimated Cost of the Total Project Including this Resolution-$5,648,202.01

Original Estimated Cost of the Total Project (Common Council Resolution File Number 140427) -$5,579,450

 

Requestor

Department of Public Works

Drafter

Infrastructure Services Division

JOSEPH C. BLAKEMAN:P. Vue

 January 10, 2017