File #: 120371    Version:
Type: Resolution Status: Passed
File created: 7/6/2012 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 7/24/2012
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $446,224.06 for a total estimated cost of these projects being $4,527,724.06.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Comptroller Certification, 2. Hearing Notice List
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
8/1/20121 MAYOR SIGNED   Action details Meeting details Not available
7/24/20121 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Not available
7/11/20121 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
7/11/20120 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Individual appearing: Mary Dziewiontkoski, Department of Public Works
Pass4:0 Action details Meeting details Not available
7/11/20121 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTIONPass4:0 Action details Meeting details Not available
7/10/20120 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
7/10/20120 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
7/10/20120 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
7/9/20120 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
7/9/20120 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
7/9/20120 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
7/9/20120 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
7/9/20120 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
7/9/20120 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
7/6/20120 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
120371
Version
Substitute 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $446,224.06 for a total estimated cost of these projects being $4,527,724.06.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $446,224.06 with the total cost estimated to be $4,527,724.06
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:
 
4th Aldermanic District
 
N. Cass St. - E. State St. to E. Juneau Ave. (SM495120058):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $173,000.  This project is anticipated to be completed during the 2013 construction season.
 
5th Aldermanic District
 
W. Beckett Ave. - N. 77th St. to W. Ruby Ave. (WT410130614):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $120,000.  This project is anticipated to be completed during the 2013 construction season.
 
W. Capitol Dr. - N. 84th St. to W. Grantosa Dr. (WT410130001):  Hydrant alteration.  (Nonassessable Water Fund Budget Line 5010 -- $1,500; Nonassessable Water Fund Budget Line 6410 -- $6,000).  The total estimated cost for this project including the requested amount is $60,000.  This project is anticipated to be completed during the 2013 construction season.
 
W. Ruby Ave. - N. 77th St. to W. Beckett Ave. (WT410130613):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $85,000.  This project is anticipated to be completed during the 2013 construction season.
 
N. 77th St. - W. Beckett Ave. to W. Ruby Ave. (WT410130612):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2013 construction season.
 
N. 94th St. - W. Burleigh St. to W. Townsend St. (WT410130005):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $15,000; Nonassessable Water Fund Budget Line 6410 -- $15,000).  The total estimated cost for this project including the requested amount is $440,000.  This project is anticipated to be completed during the 2013 construction season.
 
8th Aldermanic District
 
W. Orchard St. - S. 31st St. to S. 32nd St. (SM495120055):  Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $35,000.  This project is anticipated to be completed during the 2013 construction season.
 
S. 26th St. - W. Pierce St. to W. National Ave. (WT410130008):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $150,000.  This project is anticipated to be completed during the 2013 construction season.
 
10th Aldermanic District
 
W. Garfield Ave. - N. 53rd St. to N. 55th St. (SM495120056):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $111,000.  This project is anticipated to be completed during the 2013 construction season.
 
Zoo Interchange Reconstruction (State ID 1060-33-07) Plan Review work order #7 under WISDOT Master Contract 0696-20-13 File Number 021298:
 
100 percent WISDOT reimbursable costs for City plan review, coordination, and liaison
 
Grantor Reimbursable Paving Fund -- $49,724.06
 
These funds are to be transferred to the engineering account (ST3201202XX)
 
Previously authorized for plan review, project coordination, and liaison:  $0.00
 
The total estimated cost of total project including the requested amount is $49,724.06
 
This project is anticipated to be completed in 2018.
 
12th Aldermanic District
 
S. 10th St., W. Windlake Ave., and W. Rogers St. (Intersection) (ST211130144):  Intersection modification.  (Nonassessable Reconstruction Paving Fund -- $10,000).  The total estimated cost for this project including the requested amount is $35,000.  This project is anticipated to be completed during the 2013 construction season.
 
12th and 14th Aldermanic Districts
 
S. 11th St. - 400 feet m/l south of W. Cleveland Ave. to 100 feet m/l south of W. Harrison Ave. (SM495120054):  Relaying combined sewer and new storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $311,000.  This project is anticipated to be completed during the 2013 construction season.
 
13th Aldermanic District
 
W. Abbott Ave. - S. 21st St. to S. 23rd St. (WT410130707):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $10,000; Nonassessable Water Fund Budget Line 6410 -- $10,000).  The total estimated cost for this project including the requested amount is $210,000.  This project is anticipated to be completed during the 2013 construction season.
 
W. Bolivar Ave. - S. Howell Ave. to S. 1st Pl. (SM495120050):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $128,000.  This project is anticipated to be completed during the 2013 construction season.
 
W. Mallory Ave. - S. 22nd Pl. to S. 23rd St. (WT410130708):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $60,000.  This project is anticipated to be completed during the 2013 construction season.
 
S. 1st Pl. - W. Waterford Ave. to W. Bolivar Ave. (SM495120053):  Sanitary sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $252,000.  This project is anticipated to be completed during the 2013 construction season.
 
S. 1st St. - W. Waterford Ave. to W. Bolivar Ave. (SM495120052):  Sanitary sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $64,000.  This project is anticipated to be completed during the 2013 construction season.
 
S. 2nd St. - W. Waterford Ave. to W. Bolivar Ave. (SM495120051):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $253,000.  This project is anticipated to be completed during the 2013 construction season.
 
S. 19th St. - W. Holt Ave. to W. Morgan Ave. (SM495120059):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $108,000.  This project is anticipated to be completed during the 2013 construction season.
 
S. 22nd Pl. - W. Abbott Ave. to 325 feet south of W. Abbott Ave. (WT410130710):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $75,000.  This project is anticipated to be completed during the 2013 construction season.
 
S. 22nd St. - W. Abbott Ave. to W. Clayton Crest Ave. (WT410130709):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $10,000; Nonassessable Water Fund Budget Line 6410 -- $10,000).  The total estimated cost for this project including the requested amount is $210,000.  This project is anticipated to be completed during the 2013 construction season.
 
S. 23rd St. - W. Clayton Crest Ave. to W. Grange Ave. (WT410130706):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $10,000; Nonassessable Water Fund Budget Line 6410 -- $10,000).  The total estimated cost for this project including the requested amount is $230,000.  This project is anticipated to be completed during the 2013 construction season.
 
S. 23rd St. - W. Edgerton Ave. to 300 feet south of W. Abbott Ave. (WT410130705):  (Nonassessable Water Fund Budget Line 5010 -- $10,000; Nonassessable Water Fund Budget Line 6410 -- $10,000).  The total estimated cost for this project including the requested amount is $220,000.  This project is anticipated to be completed during the 2013 construction season.
 
S. 27th St. - W. Edgerton Ave. to W. Clayton Crest Ave. (WT410130704):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $12,000; Nonassessable Water Fund Budget Line 6410 -- $13,000).  The total estimated cost for this project including the requested amount is $350,000.  This project is anticipated to be completed during the 2013 construction season.
 
14th Aldermanic District
 
S. Adams Ave. - E. Montana St. to E. Fremont Pl. (SM495120046):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $82,000.  This project is anticipated to be completed during the 2013 construction season.
 
S. Kansas Ave. - E. Saveland Ave. to E. Warnimont Ave. (Portions in the City of St. Francis) (SM495120048):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $191,000.  This project is anticipated to be completed during the 2013 construction season.
 
E. Warnimont Ave. - S. Kansas Ave. to S. Brust Ave. (Portions in the City of St. Francis) (SM495120047):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $131,000.  This project is anticipated to be completed during the 2013 construction season.
 
E. Wilbur Ave. - S. Alabama Ave. to S. Kansas Ave. (SM495120049):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $62,000.  This project is anticipated to be completed during the 2013 construction season.
 
15th Aldermanic District
 
N. 36th St. - W. Lisbon Ave. to 200 feet m/l north of W. Lloyd St. (SM495120057):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $232,000.  This project is anticipated to be completed during the 2013 construction season.
 
;and, be it
 
Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it
 
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
 
Further Resolved, That the City Comptroller is directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
 
Requestor
Infrastructure Services Division
Drafter
MLD:dr
Npr 14
07/10/2012