File #: 210693    Version: 0
Type: Resolution Status: Passed
File created: 9/1/2021 In control: COMMON COUNCIL
On agenda: Final action: 9/21/2021
Effective date:    
Title: Resolution authorizing the City Comptroller to transfer additional funds to the previously established projects for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the construction of the West Capitol Drive (STH 190) project in various Aldermanic districts with a total estimated cost increase for the projects of $141,000, with an estimated Grantor share of $0, and an estimated City share of $141,000.
Sponsors: THE CHAIR
Indexes: GRANTS, STREET IMPROVEMENTS
Attachments: 1. 2025-19-00,70 SMA.pdf, 2. Equity Impact Statement STH 190.pdf, 3. Resolution Certification 2025-19-0070.pdf

Number

210693

Version

ORIGINAL

Reference

 

Sponsor

THE CHAIR

Title

Resolution authorizing the City Comptroller to transfer additional funds to the previously established projects for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the construction of the West Capitol Drive (STH 190) project in various Aldermanic districts with a total estimated cost increase for the projects of $141,000, with an estimated Grantor share of $0, and an estimated City share of $141,000.

Analysis

Resolution authorizing the City Comptroller to transfer additional funds to the previously established project for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the construction of the West Capitol Drive (STH 190) project in various Aldermanic districts with a total estimated cost increase for the projects of $141,000, with an estimated Grantor share of $0, and an estimated City share of $141,000.

Body

Whereas, Additional construction work has resulted in an increased cost charged against the capital improvement project; and

 

Whereas, Additional funds are, therefore, necessary to complete the construction of the project; now, therefore be it

 

Resolved, By the Common Council of the City of Milwaukee, that the City Comptroller is hereby authorized to transfer fund to the project grant chart field as follows:

 

Project Grant Value

State ID 2025-19-00

ST320150201

West Capitol Drive (STH 190); N Green Bay Ave. to N 2nd St.

 

City Share Non-Assessable Fund, Paving

ST320210000

Fund 0333

$31,000

 

Total design previously authorized $676,500.

Current estimated cost of total project including this resolution $6,966,559.

Original estimated cost of total project (Resolution File Number 150509) $3,957,000.

 

 

 

Project Grant Value

State ID 2025-19-70

ST320150210

West Capitol Drive (STH 190); N Green Bay Ave. to N 2nd St.

 

City Share Non-Assessable Fund, Paving

ST320210000

Fund 0333

$110,000

 

Total - $141,000

 

Total construction previously authorized $963,092

Current estimated cost of total project including this resolution $6,966,559.

Original estimated cost of total project (Resolution File Number 150509) $3,957,000.

 

 

Requestor

Department of Public Works

Drafter

Infrastructure Services Division

DAVID J TAPIA: C. Murphy

August 23, 2021