powered help
header-left header-center header-right
File #: 980036    Version:
Type: Resolution Status: Passed
File created: 5/5/1998 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 5/27/1998
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations.
Sponsors: THE CHAIR
Indexes: ASSESSMENTS, PUBLIC IMPROVEMENTS, SIDEWALKS, STREET IMPROVEMENTS

NUMB:

980036

VERS:

SUBSTITUTE 1

REF:

970750

XXBY:

THE CHAIR

TITL:

Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations.

ANLS:

-Analysis-

 

This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.

BODY:

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

 

16th Aldermanic District

 

S. 65th St. - W. Main St. to W. Dixon St. (878-0018-5) File Number 970750: Asphalt pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where needed, sodding, and grading. (Nonassessable Reconstruction Paving Fund 31-523---211-0001 -- $154,730; Assessable Reconstruction Paving Fund 71-523---211-0001 -- $58,840)

 

;and

 

Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and

 

Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works' Report is approved and the properties therein identified are benefited; and, be it

 

 Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.60 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital purpose subaccounts; and, be it

 

Further Resolved, That the projects do not involve any parcels of land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it

 

Further Resolved, That project S. 65th St. (878-0018-5) will be billed after January 1, 2001, but not before 12 months after the project contract has been completed.

DFTR:

INFRASTRUCTURE SERVICES DIVISION

MGL:sdp

05-15-98

980036.AFR