powered help
header-left header-center header-right
File #: 200816    Version: 0
Type: Resolution Status: Passed
File created: 10/13/2020 In control: COMMON COUNCIL
On agenda: Final action: 11/4/2020
Effective date:    
Title: Resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $47,000 for a total estimated cost of these projects being $1,000,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

 

Number

200816

Version

ORIGINAL

Sponsor

THE CHAIR

Title

Resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $47,000 for a total estimated cost of these projects being $1,000,000.

Analysis

This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed.  After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable.  A resolution will be submitted after the Public Hearing authorizing construction.  The City cost for engineering these projects is estimated to be $47,000 with the total cost estimated to be $1,000,000.

Body

Resolved, By the Common Council of the City of Milwaukee that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:

 

4th Aldermanic District

 

E. Erie St. - 700’ +/- south of N. Jackson St. to E. Summerfest Pl. (ST211200147) Install traffic calming speed hump(s). (Nonassessable Resurface Reconstruct Paving Fund -- $2,000.)  The total estimated cost for this project including the requested amount is $15,000.  This project is anticipated to be completed during the 2020-21 construction season.

 

6th Aldermanic District

E. Vienna Ave. - N. Humbolt Blvd. to N. Holton St. (ST211190140) Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund - $15,000 additional funds). The total estimated cost of this project including the requested amount is $315,000. This project is anticipated to be completed during the 2021 construction season.

 

7th Aldermanic District

 

W. Ruby Ave. - N. 36th St. to N. Sherman Blvd (ST211120114).  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $20,000, additional funds).  The total estimated cost for this project including the requested amount is $400,000.  This project is anticipated to be completed during the 2021 construction season.

 

W. Vienna Ave. - N. 35th St. to N. 41st St. (ST211140134) Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund  -- $10,000, additional funds).  The total estimated cost of this project including the requested amount is $270,000.  This project is anticipated to be completed during the 2021 construction season

 

; and, be it

 

Further Resolved, That the abutting and adjacent properties be assessed a portion of the cost, said assessment to be recommended by the Commissioner of Public Works in his report; and, be it

 

Further Resolved, That all assessments and payments be made in accordance with Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That all City departments are authorized to do engineering, surveying, preparing of plans, and estimates of cost thereof, to be utilized in the preparation of said report of the Commissioner of Public Works; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/dl

Apr 3

10 /07/2020

Technical Correction

10/22/20

MKS