File #: 101439    Version:
Type: Resolution Status: Passed
File created: 3/23/2011 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 4/12/2011
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $219,000 for a total estimated cost of these projects being $12,987,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SANITARY SEWERS, SEWERS
Attachments: 1. Hearing Notice List
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
4/18/20111 MAYOR SIGNED   Action details Meeting details Not available
4/12/20111 COMMON COUNCIL ADOPTEDPass13:0 Action details Meeting details Not available
3/31/20111 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
3/30/20110 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Individual appearing: Clark Wantoch, Department of Public Works-Infrastructure Proposed Substitute A accepted.
Pass5:0 Action details Meeting details Not available
3/30/20111 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTIONPass5:0 Action details Meeting details Not available
3/28/20110 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
3/28/20110 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
3/28/20110 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
3/28/20110 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
3/23/20110 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

 

Number

101439

Version

Substitute 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $219,000 for a total estimated cost of these projects being $12,987,000.

Analysis

This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $219,000 with the total cost estimated to be $12,987,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

 

3rd Aldermanic District

 

E. Chambers St. - N. Bremen St. to 125 feet m/l east of N. Weil St. (SM495110016):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $112,000.  This project is anticipated to be completed during the 2012 construction season.

 

5th Aldermanic District

 

Lateral Lining and Foundation Drain Disconnection/ABB (#3) (SM494110103):  Sanitary sewer lining.  (Infiltration/Inflow Reduction Fund -- $1,000).  The total estimated cost for this project including the requested amount is $9,000,000.  This project is anticipated to be completed during the 2011 construction season.

 

6th Aldermanic District

 

N. Dr. Martin Luther King Jr. Dr. - W. Keefe Ave. to N. Port Washington Ave. (SM495110026):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $154,000.  This project is anticipated to be completed during the 2011 construction season.

 

8th Aldermanic District

 

W. Burnham St. - S. 33rd St. to S. 35th St. (SM495110023):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $295,000.  This project is anticipated to be completed during the 2011 construction season.

 

S. 35th St. - 300 feet m/l north of W. Burnham St. to W. Burnham St. (SM495110024):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $143,000.  This project is anticipated to be completed during the 2012 construction season.

 

10th Aldermanic District

 

W. St. Paul  Ave. - 150 feet m/l east of N. 39th St. to N. 42nd St. (SM495110021):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $540,000.  This project is anticipated to be completed during the 2011 construction season.

 

N. 39th St. - W. St. Paul Ave. to W. Clybourn St. (SM495110022):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $109,000.  This project is anticipated to be completed during the 2011 construction season.

 

13th Aldermanic District

 

E. Armour Ave. - S. Austin St. to S. Adams Ave. (SM495110029):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $220,000.  This project is anticipated to be completed during the 2011 construction season.

 

E. Bolivar Ave. - S. Austin St. to S. Pine Ave. (SM495110019):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $216,000.  This project is anticipated to be completed during the 2012 construction season.

 

S. Quincy Ave. - E. Armour Ave. to E. Layton Ave. (SM495110017):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $193,000.  This project is anticipated to be completed during the 2012 construction season.

 

13th and 14th Aldermanic Districts

 

E. Waterford Ave. - S. Austin St. to S. Whitnall Ave. (SM495110020):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $278,000.  This project is anticipated to be completed during the 2012 construction season.

 

14th Aldermanic District

 

S. Kinnickinnic Ave. - 70 feet m/l south of E. Bay St. to 50 feet m/l south of E. Stewart St. (SM495110028):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $337,000.  This project is anticipated to be completed during the 2011 construction season.

 

S. Pine Ave. - E. Howard Ave. to E. Norwich St. (SM495110018):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $198,000.  This project is anticipated to be completed during the 2012 construction season.

 

S. Whitnall Ave. - E. Norwich Ave. to E. Waterford Ave. (SM495110025):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $207,000.  This project is anticipated to be completed during the 2011 construction season.

 

15th Aldermanic District

 

W. Wells St. - N. 35th St. to N. 37th St. (SM495110027):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $125,000.  This project is anticipated to be completed during the 2011 construction season.

 

City Wide

 

Storm Water Basin and Drain Replacement for 2011 Paving Projects (SM495110033):  (Nonassessable Sewer Maintenance Relay Fund -- $1,000).  The total estimated cost for this project including the requested amount is $500,000.  This project is anticipated to be completed during the 2011 construction season.

 

City of Greenfield

 

S. 56th St. - W. Forest Home Ave. to W. Howard Ave. (WT410110708):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $12,000; Nonassessable Water Fund Budget Line 6410 -- $13,000).  The total estimated cost for this project including the requested amount is $360,000.  This project is anticipated to be completed during the 2012 construction season.

 

;and, be it

 

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

MLD:dr

Npr 10

03/17/2011

Techinical Correction-4/8/11-tb