powered help
header-left header-center header-right
File #: 220870    Version:
Type: Resolution Status: Passed
File created: 10/11/2022 In control: COMMON COUNCIL
On agenda: Final action: 11/1/2022
Effective date:    
Title: Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $36,000 for a total estimated cost of these projects being $265,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

Number

220870

Version

Substitute 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $36,000 for a total estimated cost of these projects being $265,000.

Analysis

This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed.  After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable.  A resolution will be submitted after the Public Hearing authorizing construction.  The City cost for engineering these projects is estimated to be $36,000 with the total cost estimated to be $265,000.

Body

Resolved, By the Common Council of the City of Milwaukee that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:

 

6th Aldermanic District

 

Alley betw. W. Hopkins St., W. Townsend St., N. 22nd St., N. 23rd St. (ST212220116) Paving the alley with concrete. Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $20,000). The total estimated cost for this project including the requested amount is $150,000. This project is anticipated to be completed during the 2024-2025 construction season.

 

N. 1st St. - W. North Av. to W. Center St. (ST211210221) Concrete pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, sodding and grading. (Non-Assessable Reconstruction Paving Fund --$15,000 additional funds) The total estimated cost of this project including the requested amount is $1,100,000. This project is anticipated to be completed during the 2024-25 construction season.

 

7th Aldermanic District

 

Alley betw. W. Courtland Av., W. Derby Pl., N. Sherman Bl., N. 42nd St. (ST212220115): Paving the alley with concrete. Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $10,000). The total estimated cost for this project including the requested amount is $70,000. This project is anticipated to be completed during the 2024-2025 construction season.

 

10th Aldermanic District

 

Alley betw. W. Galena St., W. Vliet St., N. 51st St., N. 52nd St. (ST212220117) Paving the alley with concrete. Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $6,000). The total estimated cost for this project including the requested amount is $45,000. This project is anticipated to be completed during the 2024-2025 construction season.

 

; and, be it

 

Further Resolved, That the abutting and adjacent properties be assessed a portion of the cost, said assessment to be recommended by the Commissioner of Public Works in his report; and, be it

 

Further Resolved, That all assessments and payments be made in accordance with Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That all City departments are authorized to do engineering, surveying, preparing of plans, and estimates of cost thereof, to be utilized in the preparation of said report of the Commissioner of Public Works; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Holly Rutenbeck/TW

APR3 Sub

10/14/2022