Number
090511
Version
SUBSITITUTE 2
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $209,000 for a total estimated cost of these projects being $5,860,000.
Analysis
This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed. After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable. A resolution will be submitted after the Public Hearing authorizing construction. The City cost for engineering these projects is estimated to be $209,000 with the total cost estimated to be $5,860,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:
1st Aldermanic District
W. Lawn Ave. - N. 13th St. to N. Green Bay Ave. (ST211090114) File Number 071574: Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $5,000 Additional Funds). The total estimated cost for this project including the requested amount is $35,000. This project is anticipated to be completed during the 2010 construction season.
2nd Aldermanic District
N. 66th St. - W. Capitol Dr. to W. Congress St. (ST211090119) File Number 080004: Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $8,000 Additional Funds). The total estimated cost for this project including the requested amount is $30,000. This project is anticipated to be completed during the 2010 construction season.
3rd and 4th Aldermanic Districts
N. Oakland Ave. - N. Cambridge Ave. to m/l north of E. Windsor Pl. (ST211040106): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $22,000). The total estimated cost for this project including the requested amount is $46,000. This project is anticipated to be completed during the 2010 construction season.
6th Aldermanic District
N. 4th St. - W. McKinley Ave. to W. Walnut St. (ST211110102): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $30,000). The total estimated cost for this project is $30,000. This project is anticipated to be completed during the 2010 construction season.
8th Aldermanic District
W. Mitchell St. - S. Layton Blvd. to S. 32nd St. (ST211040114): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $16,000). The total estimated cost for this project including the requested amount is $25,000. This project is anticipated to be completed during the 2010 construction season.
S. 31st St. - W. Hayes Ave. to W. Lincoln Ave. (ST211020123): Paving the roadway with concrete. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $10,000). The total estimated cost for this project including the requested amount is $120,000. This project is anticipated to be completed during the 2011 construction season.
9th Aldermanic District
W. County Line Rd. - N. 68th St. to N. 91st St./N. Swan Rd. (ST211100132): Paving the roadway with asphalt (Rural cross section). Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $20,000). The total estimated cost for this project including the requested amount is $2,300,000. This project is anticipated to be completed during the 2010 construction season.
W. County Line Rd. - N. 91st St./N. Swan Rd. to N. 124th St./N. Wasaukee Rd. (ST211100131): Paving the roadway with asphalt (Rural cross sectioin). Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $20,000). The total estimated cost for this project including the requested amount is $2,900,000. This project is anticipated to be completed during the 2010 construction season.
N. 80th St. - W. Mill Rd. to W. Green Tree Rd. (ST21110107): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $15,000). The total estimated cost for this project including the requested amount is $23,000. This project is anticipated to be completed during the 2010 construction season.
13th Aldermanic District
S. 1st St. - A point 170 feet m/l south of W. Armour Ave. to a point 160 feet m/l north of W. Allerton Ave. (ST211100101) File Number 080910: Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $8,000 Additional Funds). The total estimated cost for this project including the requested amount is $19,000. This project is anticipated to be completed during the 2010 construction season.
14th Aldermanic District
E. Lincoln Ave. - S. Kinnickinnic Ave. to S. 1st St. (ST211110101): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $45,000). The total estimated cost for this project is $45,000. This project is anticipated to be completed during the 2010 construction season.
15th Aldermanic District
N. 29th St. - W. Meinecke Ave. to W. Center St. (ST211110103): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $10,000). The total estimated cost for this project including the requested amount is $287,000. This project is anticipated to be completed during the 2011 construction season.
; and, be it
Further Resolved, That the abutting and adjacent properties be assessed a portion of the cost, said assessment to be recommended by the Commissioner of Public Works in his report; and, be it
Further Resolved, That all assessments and payments be made in accordance with Section 115-42 of the Milwaukee Code of Ordinances; and, be it
Further Resolved, That all City departments are authorized to do engineering, surveying, preparing of plans, and estimates of cost thereof, to be utilized in the preparation of said report of the Commissioner of Public Works; and, be it
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
Requestor
Infrastructure Services Division
Drafter
Mld:dr
Apr 1
09/10/09