powered help
header-left header-center header-right
File #: 090760    Version:
Type: Resolution Status: Passed
File created: 10/13/2009 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 11/3/2009
Effective date:    
Title: Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $222,692.60 for a total estimated cost of these projects being $4,370,886.60.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Fiscal note, 2. Cover Letter, 3. Hearing Notice List
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
11/12/20091 MAYOR SIGNED   Action details Meeting details Not available
11/3/20091 COMMON COUNCIL ADOPTEDPass14:0 Action details Meeting details Not available
10/21/20091 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Individual present: Clark Wantoch, Dept. of Public Works
Pass5:0 Action details Meeting details Not available
10/19/20090 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
10/16/20090 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
10/16/20090 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
10/16/20090 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
10/16/20090 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
10/16/20090 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
10/16/20090 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
10/16/20090 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
10/16/20091 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
10/13/20090 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

090760

Version

SUBSTITUTE 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $222,692.60 for a total estimated cost of these projects being $4,370,886.60.

Analysis

This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed.  After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable.  A resolution will be submitted after the Public Hearing authorizing construction.  The City cost for engineering these projects is estimated to be $222,692.60 with the total cost estimated to be $4,370,886.60.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:

 

3rd Aldermanic District

 

N. Cambridge Ave. - E. Locust St. to E. Kenwood Blvd. (ST211100138): Install traffic calming devices. (Nonassessable Reconstruction Paving Fund -- $5,000). The total estimated cost for this project including the requested amount is $10,000.  This project is anticipated to be completed during the 2010 construction season.

 

4th Aldermanic District

 

W. McKinley Blvd. - N. 27th St. to N. 35th St. (ST211110104): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $58,000).  The total estimated cost for this project including the requested amount is $984,000.  This project is anticipated to be completed during the 2011 construction season.

 

6th Aldermanic District

 

N. 3rd St. - W. Concordia Ave. to W. Keefe Ave. (ST211100139): Install traffic calming devices.  (Nonassessable Reconstruction Paving Fund -- $5,000).  The total estimated cost for this project including the requested amount is $7,000.  This project is anticipated to be completed during the 2010 construction season.

 

N. 15th St. - W. Burleigh St. to W. Ring St. (ST211100140): Install traffic calming devices. (Nonassessable Reconstruction Paving Fund -- $5,000).  The total estimated cost for this project including the requested amount is $7,000.  This project is anticipated to be completed during the 2010 construction season.

 

8th Aldermanic District

 

W. Canal St. - Miller Park Ring Rd. to Falk Dr. (Canal Phase 2-Sanitary) (SW170050101) File Number 041468: Expansion of capacity.  (Assessable Expansion of Capacity Sewer Fund -- $72,386.60 Additional Funds).  The total estimated cost for this project including the requested amount is $2,087,071.60.  This project has been completed.

 

W. Canal St. - Miller Park Ring Rd. to Falk Dr. (Canal Phase 2-Storm) (SW170050112) File Number 041468: Expansion of capacity. (Assessable Expansion of Capacity Sewer Fund -- $47,306 Additional Funds).  The total estimated cost for this project including the requested amount is $1,111,815.  This project has been completed.

10th Aldermanic District

 

W. Vienna Ave. - N. 66th St. to N. 68th Street, including N. 66th Street - W. Vienna Ave. to W. Melvina St. (ST211080151): Install traffic calming devices. (Nonassessable Reconstruction Paving Fund -- $5,000).  The total estimated cost for this project including the requested amount is $10,000.  This project is anticipated to be completed during the 2010 construction season.

 

13th Aldermanic District

 

W. Holmes Ct. - S. 18th St. to a point west of S. 18th St. (ST211100142): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $5,000).  The total estimated cost for this project including the requested amount is $65,000.  This project is anticipated to be completed during the 2011 construction season.

 

W. Vogel Ct. - S. 18th St. to a point west of S. 18th St. (ST211100141): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $5,000).  The total estimated cost for this project including the requested amount is $65,000.  This project is anticipated to be completed during the 2011 construction season.

 

14th Aldermanic District

 

S. Brisbane Ave. - E. Deer Pl. to E. Clarence St. (ST211100134): Install traffic calming devices. (Nonassessable Reconstruction Paving Fund -- $5,000).  The total estimated cost for this project including the requested amount is $7,000.  This project is anticipated to be completed during the 2010 construction season.

 

15th Aldermanic District

 

W. Lloyd St. - N. 11th St. to N. 13th St. (ST211100135): Install traffic calming devices. (Nonassessable Reconstruction Paving Fund -- $5,000).  The total estimated cost for this project including the requested amount is $10,000.  This project is anticipated to be completed during the 2010 construction season.

 

N. 46th St. - W. North Ave. to W. Meineke Ave. (ST211100133): Install traffic calming devices. (Nonassessable Reconstruction Paving Fund -- $5,000).  The total estimated cost for this project including the requested amount is $7,000.  This project is anticipated to be completed during the 2010 construction season.

 

; and, be it

 

Further Resolved, That the abutting and adjacent properties be assessed a portion of the cost, said assessment to be recommended by the Commissioner of Public Works in his report; and, be it

 

Further Resolved, That all assessments and payments be made in accordance with Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That all City departments are authorized to do engineering, surveying, preparing of plans, and estimates of cost thereof, to be utilized in the preparation of said report of the Commissioner of Public Works; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

MLD:dr

Apr 3